a) It was agreed that the scheme for bollards under the M4 in Oxford Avenue, Heston would be prioritised for allocation of funding when identified and available. b) It was agreed that the scheme for widening the carriageway in The Glen, Southall would be prioritised for allocation of funding when identified and available, subject to further discussion by the Committee concerning the details. c) It was agreed that a scheme for a crossing by Cranford Community College would be included in a future list of priorities. d) Environmental improvements listed in appendix 3 of the report were agreed for prioritisation when funding was identified and available.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Heston and Cranford Area Committee (Monitoring)
Summary
To advise members of proposed Environmental Improvement Schemes to the public highway, and seek approval to progress these schemes to implementation when funding is available.
Recommendations
1.1That Members note the contents of the report
1.2That Members consider the proposed Environmental Improvement Schemes in 3.1 and 3.2 and if approved prioritise these for allocation of funding along with the remaining environmental improvement proposals listed in appendix 3, from Capital or S106 funding when identified and available.
Background
2.1The Executive, at its meeting on 3rd January 2006, released the remaining ‘frozen’ capital budgets for 2005/06 and 2006/07 with the Heston & Cranford Area receiving a total of £54k for environmental improvements. At the monitoring meeting held during 2005/06 members approved the allocation of all of these funds to various environmental and highway improvements within the Heston and Cranford Area
2.2This year officers from Environmental Services have received suggestions from local Ward Councilors, members of the public and local businesses for improvements to the street scene and where appropriate these have been carried out using available resources from existing revenue budgets. However some of the suggestions received were for activities, which could not be met from existing revenue budget allocations and therefore may be considered under the conditions of the capital allocations.
2.3Proposed environmental improvements have been listed in par 3.0 funding. All proposals listed are to be considered and prioritised for implementation by Members of the Area Monitoring Committee.
3.0PROPOSALS
3.1Oxford Avenue Heston. ( see appendix 1 )
H&C Monitoring 25/01/2007 3.1.1 Residents and police have highlighted the area of footway under the M4 motorway as a site where because of its location away from residential properties has been used for antisocial behaviour. The M4 motorway is carried over Oxford Avenue on an elevated structure that if targeted by terrorist groups would have severe consequences on the traffic flows in and out of London from the West.
3.1.2 Measures have been carried out recently to improve the lighting of this area and reduce the potential for antisocial behaviour. However Oxford Avenue is the only access for vehicles to Durham Avenue and it is proposed to install bollards and realign the kerb to prevent vehicles parking illegally on the footway or under the elevated section of the M4. The estimated cost of carrying out these works is £10k
3.2The Glen, Southall.( see appendix 2 )
3.2.1 The Glen, is divided by a grassed central reservation that is being damaged opposite nos 25 – 36 by vehicles, particularly large service vehicles, having to mount the verge to negotiate the bend.
3.2.2 It is proposed to widen the carriageway by realigning the kerb opposite nos 25 – 36 to allow vehicles to manoeuvre the bend. The estimated cost of carrying out these works is £7.5k
Financial implications
4.1Capital allocation. There are currently no funds available from the Area Committees capital allocation for Environmental Improvements.
4.2Section 106 Environmental Improvements: - There is currently a total of £7,000 unallocated S106 monies for traffic & highways that is no longer required and members have agreed for officers to seek a deed of variation to use this funding for environmental improvements.
5.0HEAD OF FINANCE COMMENTS
5.1( to follow )
6.1That the contents of the report be noted.
6.2That Members consider the proposed Environmental Improvement Schemes in 3.1 and 3.2 and if approved prioritise these for allocation of funding along with the remaining environmental improvement proposals listed in appendix 3, from Capital or S106 funding when identified and available.
7.0ENVIRONMENTAL IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Heston and Cranford Area Committee (Monitoring) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.