Central Infrastructure Report - John Reynolds

Noted Committee 1 paper

Central Hounslow Area Committee (monitoring) noted this item on Thursday 1 February 2007. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

Resolved - a) To note the contents of the report b) To agree the purchase of a ‘Domehawk’ portable CCTV camera for siting on lamp column 18 located in Kingsley Road at a cost of £15,000 from the Area Committee Capital Allocation c) To agree the purchase of a ‘Domehawk’ portable CCTV camera for siting on lamp column 10 located in Chatsworth Crescent at a cost of £15,000 to be allocated from the Area Committee Capital Allocation.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Central Hounslow Area Committee (monitoring)

Summary

This report advises Members of the Area Committee of the proposals for providing CCTV in Kingsley Road and Chatsworth Crescent, together with the estimated cost for each of these proposals.

Recommendations

1.1That Members note the contents of the report and consider the options available.

1.2That Members consider the proposals set out in 3.1 and if approved, select either option (a) or option (b) for implementation and agree to the allocation of funds from the Area Committee Capital currently available.

1.3That Members consider the proposals set out in 3.2 and if approved for implementation, agree to the allocation of funds from the Area Committee Capital currently available.

Background

2.1Members have supported the use of CCTV to deter crime and anti social behaviour in their area and over the last two years have provided funding from their capital allocation and through S106 for 6 ‘Domehawk’ portable CCTV cameras. These cameras currently record all data on an internal hard drive that may be downloaded by the police or authorised persons for evidence or during an investigation. However as part of the Borough Wide CCTV Network Project these type of cameras will be upgraded to enable remote control and transmission of all data back to the CCTV Control Room where they will be recorded 24/7 and monitored 24 hours a day in accordance with the Code of Practice for the Town Centre

2.2The ‘Domehawk ‘ cameras are portable and capable of being re located within the Central Hounslow Area. Currently they are located in the following roads, and have improved the environment for the community as a whole by reducing the fear of crime, and assisting the police in dealing with crime and incidents of anti social behaviour.

ƒ Whitton Road 2 no

Central Hounslow Committee (Monitoring) 1 Feb 2007 page 1 of 5 CCTV Proposals Report ƒ Midsummer Avenue 1 no ƒ Staines Road 1 no ƒ North Drive 1 no ƒ Bath Road Hounslow West 1 no

2.3Both members and the police have recently been made aware of an increase in the fear of crime and incidents of anti social behaviour in Kingsley Avenue and in Chatsworth Crescent, and have asked officers to look at the possibility and costs of providing a CCTV camera for both these locations.

3.0PROPOSALS

3.1Proposal 1 – Kingsley Road: It is proposed to locate a camera at the junction of Kingsley Road on lamp column no 18 ( see appendix 1 ) that could be used to monitor Kingsley Avenue and Kingsley Road to the north and south of the junction. There are two options for the type of camera that may be used,

Option (a)- siting a fixed camera on lamp column 18 that would transmit data via cable back to the HTC CCTV Control Room where it would be recorded 24/7, and monitored 24 hours a day along with the other fixed CCTV Cameras in the Town Centre. This option would require extension to the existing CCTV fibre network in Kingsley Road that currently terminates south of Hounslow East Tube Station.

The estimated cost of providing this option would be £35k.

Option (b) – siting a ‘ Domehawk ‘ portable CCTV camera on lamp column 18 on Kingsley Road. The images from this camera would currently be recorded 24/7 on an internal hard drive and downloaded by the Police or other authorised persons when needed for evidence or during an investigation. However as part of the Borough Wide CCTV Network Project these type of cameras will be upgraded to enable remote control and transmission of all data back to the CCTV Control Room where they will be recorded 24/7 and monitored 24 hours a day in accordance with the Code of Practice for the Town Centre

The estimated cost of providing this option is £15k

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Central Infrastructure Report: John ReynoldsReport 62 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Central Infrastructure Report - John ReynoldsThis decision
  2. Central Infrastructure Schemes Progress Jan 2006.Noted

More from Hounslow Central Hounslow Area Committee (monitoring)

All decisions
MeetingDecisionOutcome
24 Mar 2011 S.106 Funding for Environmental Improvement SchemesThat the allocation of the sums available for the proposed works, totalling £308,155.19 as set out in Appendix 1 of t... Approved Open
20 Jan 2011 Appointment of Co-opted MembersThat [name removed], [name removed] and [name removed] be appointed at Co-opted Members to Central Hounslow Area Comm... Decided Open
18 Mar 2010 Declarations of Interest and any other Communication from MembersCouncillor Sharma presented a petition in objection to the red bus route opposite Hounslow West Tube station. Action:... Decided Open
18 Mar 2010 Minutes of the meeting held on 3 December 2009Agreed. Agreed Open
18 Mar 2010 Minutes of the meeting held on 21 January 2010Agreed, with the following addition: Councillor L. Davies asked the Area Committee for funding to support the Wii Oly... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies