The purpose of this report is to seek the Executive’s approval to use Parking Reserve Account to fund necessary Parking and Traffic projects.
2.1That Members note the content of this report and agree the use of Parking Reserve Account monies to fund the following Parking and Traffic projects:
(a) Implementation of the ParkMap system for managing traffic management orders.
(b) The networking of the Metric pay and display machines, allowing for remote control of machines and saving of officer time, as well as the provision of management information.
(c) Borough-wide survey of public highway parking signs and road markings compliance. 3.0 BACKGROUND
3.1This reports seeks permission to assign monies from the Parking Reserve Account to specific projects outlined in this report. Parking and Traffic have identified a number of projects which will improve efficiency, performance and professionalism of the services delivered, for which funding this is required. These are detailed in the next section. Members should note there have been two other reports also requesting funding from the PRA. These are
a) CPZ Review b) Pavement Parking
4.0PROJECTS FOR WHICH FUNDING IS REQUESTED
4.1The ParkMap project will bring numerous benefits listed in Appendix 1, and was approved by the Programme Management Control Group (PMCG) in July 2006. Currently traffic management orders are manually organised with a complicated indexing system. They require consolidation. The ParkMap system enables easy consolidation as well as maintaining a history of orders and actions. All the data relating to the traffic orders can be shown pictorially for ease of use. The Traffic section will benefit from being able to consolidate and manage the traffic orders. The Parking section will benefit from ease of use wasting less time when considering challenges and building evidence for appeals. It is also considered good practice to share traffic management orders on the web for the public to refer to. Without this system, it would not be possible to share this complex information with the public. The visual representation enables universal understanding of their content. This project requires funding of £82,300.
4.2The Metric networking project will result in efficiencies (detailed in Appendix 2) as well as management information not currently available, and was also approved by the PMCG in July 2006. Currently machines are maintained by an officer responding to reports of malfunction. Once the machines are networked, the information on their state (coin box high; incorrect time etc) will be reported to a server enabling the maintenance team to visit those machines as soon as they fail or before the problem prevents the machine being used. The Parking teams will save time and produce evidence on faults and machine use for adjudication, whilst both the Parking and Traffic teams will benefit from management information on parking habits which is not currently available. This project requires funding of £30,000.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Parking Reserve Account: Funding of Traffic and Parking ProjectsReport | 33 KB | DownloadRead as text |
Follow Executive at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Mar 2011 | Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. | Decided | Open |
| 8 Mar 2011 | Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... | Decided | Open |
| 8 Mar 2011 | Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. | Noted | Open |
| 8 Mar 2011 | Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... | Agreed | Open |
| 8 Mar 2011 | Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.