Resolved
That the report which identified: spend to the end of September 2007; predicted capital outturn for 2007/08; any potential overspends and key pressure areas within the capital programme be noted
Executive noted this item on Tuesday 8 January 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report which identified: spend to the end of September 2007; predicted capital outturn for 2007/08; any potential overspends and key pressure areas within the capital programme be noted
Contact: Lorelei Watson Tel: 020 8583 2310 E-Mail: [email protected]
Executive: 8 January 2008
CAPITAL MONITORING 2007/08
Report of Councillor McGregor
Summary This report: • identifies spend to the end of September 2007 and predicted capital outturn for 2007/08; and • highlights any potential overspends in the capital programme; and • discusses the key pressure areas within the capital programme;
1.0RECOMMENDATION 1.1 To note the contents of the report.
2.0THE CAPITAL BUDGET 2.1 The budget constitutes that reported to Council on 6 March 2007, adjusted for slippage and additional specific funding.
2.2The budget below excludes the frozen schemes, since the purpose of this report is to monitor spend against relevant budgets. There are currently £1m of frozen schemes. These are £600k for IT Strategy and £400k for Streetscene as agreed at Council on 7 March 2006.
2.3We have received around £3.9m of funding since the Quarter 1 Capital Monitoring Report. The most significant addition is of £2.25m for Decent Homes for Vulnerable Households where Hounslow is the lead authority for 6 West London authorities.
2.4New corporate funding has been agreed solely for: • Civic Centre – Council Chamber audio • accommodation for PIP team in antechamber • repair of houses in Holloway Street
All other new financing is from external sources.
3.0CAPITAL PAYMENTS AND OUTTURN PROJECTION 3.1 Cash payments to date, as at the end of September 2007, are £11.9m as shown in Table 1, below. Table 1 – Capital Payments to end of September 2007 Department Budget Spend to Date £'000 £'000 % Chief Executives Department - CED 3,571 624 17% CED – Leisure 580 49 8% LLLCS (Education) 22,668 4,328 19% SMPP 9,440 1,793 19% Housing and Community Services – HCS HCS - Community Services 1,590 500 31% HCS - Housing General Fund 16,059 1,254 8% HCS - Housing Revenue Account 32,708 3,228 10% Area Committees 881 96 11% TOTAL 87,496 11,872 14%
3.2Spend to date represents 14% of the capital budget. Traditionally capital payments are loaded towards the end of the financial year, and the profiling of capital payments reflects this.
3.3The capital outturn projection for 2007/08 is based on departmental estimates. Current projections indicate programme slippage of £12.1m, approximately 14% of the capital programme. The slippage identified is managed slippage where projects have been identified and are underway but the phasing of expenditure is such that full spend will not take place in the current year. Table 2 summarises estimated outturn compared to budget. Budgets include spend not yet allocated, which accounts for projected spend being different to slippage.
Table 2 – Projected Outturn Projected Projected Department Budget spend Variance Spend £'000 £'000 £'000 % Chief Executives Department – CED 3,571 2,415 1,156 68% CED – Leisure 580 580 0 100% LLLCS (Education) 22,668 21,246 1,423 94% SMPP 9,440 9,440 0 100% Housing and Community Services – HCS HCS - Community Services 1,590 1,486 104 93% HCS - Housing General Fund 16,059 6,832 9,227 43% HCS - Housing Revenue Account 32,708 14,486 18,222 44% Area Committees 881 796 85 90% TOTAL 87,496 57,280 30,216 65%
3.4The projected outturn has been produced in consultation with departmental representatives. It would be prudent to expect some slippage in addition to that currently projected, especially as spend is projected to be the entire budget for SMPP, which makes up 11% of the total capital budget. 4.0 POTENTIAL OVERSPENDS 4.1 Potential overspends identified by responsible officers relate primarily to: a) Key Site 1: a detailed report went to Executive on the 6 November 2007 requesting additional budget to cover spend in this year and subsequent years for covering negotiations on phase 2 of the development;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Monitoring: 2nd QuarterReport | 21 KB | DownloadRead as text |
PDF |
Capital Monitoring 2nd Q AppendixAppendix | 236 KB | Download |
Follow Executive at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Mar 2011 | Minutes of the meeting held on 8 February 2011The minutes of the meeting held on 8 February 2011 were confirmed. | Decided | Open |
| 8 Mar 2011 | Minutes of the meeting held on 15 February 2011The minutes of the meeting held on 15 February 2011 were confirmed, with one amendment – page 21, paragraph 2 – amend... | Decided | Open |
| 8 Mar 2011 | Quarter 3 (October - December 2010) Quarterly Performance Management Pack 2010/11The report was noted. | Noted | Open |
| 8 Mar 2011 | Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The... | Agreed | Open |
| 8 Mar 2011 | Monthly Revenue Financial Monitoring - 31 December 2010The recommendations of the report were agreed. The recommendations of the report were agreed, namely that: The Execut... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.