RESOLVED – (a) That, subject to t he words “sheltered accommodation” being replaced by the term “residential accommodation” in proposal HCS3A, and proposals CSLL4 and CSLL7 being withdrawn, the budget savings attached at Appendix A of the report be approved and will form part of the 2008/09 budget due to be set on 4th March 2008. (b) That this Council notes the amendments tabled by Councillors Lily Bath and Ruth Cadbury which, if both agreed, would reduce the amount of efficiency savings by £185 000. If added to the amount of budget amendments suggested by various members of the Labour Group at the 29 th January 2008 meeting this would total £860 800. Further to the motion tabled without notice by Councillors Bowen and Paul Fisher at the 29 th January 2008 meeting, this Council again notes that the amendments tabled this evening reconfirms the fact that keeping council tax down for residents who endured a 100% increase between 1997 and 2006 under the previous Labour administration is a very low priority for the current members of the Labour Group. Council again urges the Labour Group to think again about those who have suffered the most under previous increases, such as hard working families and those on fixed incomes.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.1The budget savings attached at Appendix A are approved and form part of the 2008/09 budget due to be set on 4 March 2008.
2.0Local Government Finance Settlement
2.1The three-year picture is one of constraint in public spending as a whole. In local government, this has meant that in the three-year financial settlement, councils will experience the tightest parameters in terms of grant allocation since 1997. The provisional settlement announced in December gave Hounslow the minimum increase in grant over the three-year period.
2.2The final grant settlement was received on the 24th January. We had an increase in grant of £228k for 2008/09. This translates into an extra £694k over the three-year settlement period. Most authorities at the floor had increases in their 2008/09 cash figure for formula grant. The primary reason for this was due to the addition of £36.6m into the settlement relating to Public Law Family Fee increases. The new formula grant figures for Hounslow are in the table below. The authority's baseline 2007/08 grant has been adjusted and hence although the cash grant figures increase the changes year on year remain unaltered from the provisional settlement. Grant floors are paid for by 'scaling back' grant increases above the floor and hence 2 more London boroughs move under the floor, meaning that 29 boroughs are now under the floor.
2008/09 2009/10 2010/11 Formula grant (£m) 88.7 90.1 91.4 Increase from previous year (£m) 1.7 1.5 1.3 Increase from previous year (%) 2.0 1.8 1.5
1 3.0 Budget Savings Proposals
3.1The Council is continuing its preparations for setting the 2008/09 budget in the context of the poor funding settlement discussed above, and the Hounslow Plan objectives to keep council tax as low as possible.
3.2Savings from the Performance Improvement Program will not be fully on stream during 2008/09; therefore the Council needs to identify savings to fill the gap. We presented an initial tranche of savings to Borough Council on 29th January, totalling £3.7m; and informed the Council that further proposals would be presented on or before the council tax setting meeting on 4th March.
3.3We have identified a further tranche of savings, which are recommended for implementation, totalling £3.4m. A schedule of these proposals is attached at Appendix A.
4.0Comments of the Director Legal Services
4.1The Director’s comments have been included within the body of the report.
5.0Comments of the Director of Finance
5.1The whole of this report deals with financial issues.
Background papers
Budget Working Papers including “red book” and associated savings schedules. Budget & Performance Scrutiny Panel Papers 15/11/07, 19/11/07, 30/11/07, 06/12/07, 18/12/07 and 19/12/07 Letter to John Healey on Formula Grant Consultation Paper - 9/10/07 Brief tabled at meeting with John Healey - 18/12/07 Representation letter on provisional grant settlement - 3/12/08 Letter to Mayor of London on GLA Draft Budget - 11/1/08 Report to Borough Council – 29/1/08
This report has been or is due to be considered by: Borough Council
This report is relevant to the following wards/areas: All
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.