Central Hounslow Area Committee (Planning) deferred this item on Thursday 14 February 2008. Below is the council's own wording, with the papers it was decided on.
Resolved – a) That the committee considers it expedient, to defer the issuing of an enforcement notice in relation to 45 Alexandra Road, Hounslow until 25 February 2008 to allow the owner to comply with the enforcement officers instructions. b) That should the owner fail to comply with enforcement officers instructions by 25 February 2008 the committee considers it expedient, having regard to the provisions of the Unitary Development Plan, and all material considerations, to grant authority for all necessary steps to be taken for the preparation, issue and service of an enforcement notice in relation to 45 Alexandra Road, Hounslow requiring within 3 months:- The removal of the front canopy and pillars; and Removal of all resultant debris or other paraphernalia associated with the unauthorised use. AND: The institution of any necessary legal proceedings in the event of non-compliance with the above enforcement notice, pursuant to Section 179 of the Town and Country Planning Act 1990 (“TCPA 1990”) The carrying out of works in default under Section 178 TCPA 1990 in the event of non-compliance with the enforcement notice and the recovery of the Council’s costs of doing this.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Central Hounslow Area Committee (Planning)
Recommendation
1.1That the Committee considers it expedient, having regard to the provisions of the Unitary Development Plan, and all material considerations, to grant authority for:
1.2All necessary steps to be taken for the preparation, issue and service of an enforcement notice in relation to 45 Alexandra Road, Hounslow requiring within three calendar months:
• The removal of the front canopy and pillars; and
• Removal of all resultant debris; and for
The institution of any necessary legal proceedings in the event of non-compliance with the above enforcement notice, pursuant to Section 179 of the Town and Country Planning Act 1990
The carrying out of works in default under Section 178 of the Act in the event of non- compliance with the enforcement notice, including the recovery of the Council’s costs in carrying out such work.
2.0SITE DESCRIPTION
2.1The property is a detached two-storey house on the northern side of Alexandra Road. The canopy that is the subject of this report is located at the front of the property and extends from the main door across to the side extension. 3.0 PLANNING HISTORY AND OTHER RECORDS
Planning Records
No planning history relating to the canopy.
3.1Other Council Records
The aerial photographs from 2003 show that the canopy had not been built. Therefore it is not immune under the four-year rule.
4.0ENFORCEMENT HISTORY, INVESTIGATION AND EVIDENCE. 4.1 On 12 February 2007 it was brought to the attention of the enforcement team that a large canopy had been erected at 45 Alexandra Road. A site inspection by a planning enforcement officer on 16 February 2007 subsequently established that the canopy had been constructed and measured 3.5m high, 2.08m deep and 6.75m wide. 4.2 Further site visits were conducted on 16 February 2007 and 9 May 2007 to inspect the side extension that was believed to have been used as a separate residential unit. This case was subsequently resolved. The breach of planning control in relation to the canopy was also discussed during these visits.
4.3A letter was sent to the owner of 45 Alexandra Road on 14 May 2007 requesting that the owner submit a planning application in an attempt to regularise the breach, or remove the canopy. As no response had been received a further letter was sent on 12 June 2007.The letter requested that the case officer be contacted within 7 days. 4.4 A letter was received on 11 July 2007 claiming that the householder was awaiting the return of their builder in August before any work could be carried out. 4.5 An enforcement officer re-visited the site on 2 November 2007 and noted that the entire construction was still in existence. Following this a letter was sent on 2 November 2007 stating that a site visit would be carried out within 14 days to assess whether the canopy had to be reduced in size. The letter stated that, if no action had been taken, enforcement action against the structure would be considered. 4.6 On 5 November the owner called requesting a site visit to be carried out so she could be clear what elements of the canopy need to be removed. A planning enforcement officer conducted a site visit in 6 November and advised the owner that she would have to remove the canopy completely. 4.7 The picture below shows the front canopy and pillars at 45 Alexandra Road, Hounslow.
5.0ANALYSIS
5.1Under Section 172 of the Town and Country Planning Act 1990 (as amended), the Council has the power to take enforcement action where it assesses that a breach of planning control has resulted in material harm in planning terms.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Central Hounslow Area Committee (Planning) at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.