Sustainable Development Committee agreed this item on Monday 10 March 2008. Below is the council's own wording, with the papers it was decided on.

Item113

Resolved

Enforcement action agreed.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Sustainable Development Committee

Recommendation

1.1That the Committee considers it expedient, having regard to the provisions of the Unitary Development Plan, and all material considerations, to grant authority for:

1.2All necessary steps to be taken for the preparation, issue and service of an enforcement notice in relation to 72 Burns Way, Hounslow requiring within three calendar months:

• The removal of the front canopy; and

• Removal of all resultant debris; and for

The institution of any necessary legal proceedings in the event of non-compliance with the above enforcement notice, pursuant to Section 179 of the Town and Country Planning Act 1990, and

The carrying out of works in default under Section 178 of the Act in the event of non- compliance with the enforcement notice, including the recovery of the Council’s costs in carrying out such work.

2.0SITE DESCRIPTION

2.1The property is a semi-detached two-storey house on the southern side of Burns Way. The canopy that is the subject of this report is located at the front of the property and extends from the main door across to the right hand side of the property.

2.2Numbers 68 and 70 have similar canopies, however these were built prior to the adoption of the Council’s current guidelines and are therefore immune to enforcement action. The attached house number 74 does not have a porch or canopy. 3.0 PLANNING HISTORY AND OTHER RECORDS

Planning Records

No planning history relating to the canopy.

3.1Other Council Records

The aerial photographs from 2003 indicate that the canopy had not been built. Therefore it is not immune under the four-year rule.

4.0ENFORCEMENT HISTORY, INVESTIGATION AND EVIDENCE.

4.1Following a request by the Heston and Cranford Area Committee, a review of front extensions along Burns Way on 11 September 2007 established that a canopy had been constructed at the front of 72 Burns Way measuring 6.5m wide and 1m deep. 4.2 A letter was sent to the owner on 11 September 2007 requesting that the owner submit a planning application in an attempt to regularise the breach, or remove the canopy. 4.3 As no response had been received, a further letter was sent on 9 January 2008. The letter requested that the case officer be contacted within 10 working days to confirm the owner’s intentions in writing. 4.4 An enforcement officer re-visited the site on 25 January 2008 and noted that the canopy was still in existence.

4.5The picture below shows the front canopy and pillars at 72 Burns Way, Hounslow. 4.6 The picture below shows the properties to the left of 72 Burns Way.

4.7The picture below shows the properties to the right of 72 Burns Way. 5.0 ANALYSIS

Expediency in general

5.1Under Section 172 of the Town and Country Planning Act 1990 (as amended), the Council has the power to take enforcement action where it assesses that a breach of planning control has resulted in material harm in planning terms.

5.2Guidance as to how to apply this power and when a Council should find enforcement action expedient is contained in PPG18 and Circular 10/97, both entitled 'Enforcing Planning Control'. The government urges local planning authorities to use enforcement action as a last resort. Reports are not brought forward to committee unless it has been concluded that there is no other course of action available.

5.3In addition to Government guidance the statutory Development Plan sets criteria against which to judge whether a breach of planning control is unacceptable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
72 Burns Way, HestonReport 311 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. 72 Burns Way, HestonThis decision
  2. Burns Way Consultation ReportApproved
  3. Burns Way Consultation updateNoted
  4. Burns Way/Shelley Crescent CPZ UpdateNoted
  5. Proposed CPZ on Burns Way, Browning Way, and Shelly Crescent (Mark Frost)Decided
  6. 64 Burns Way, HestonApproved

More from Hounslow Sustainable Development Committee

All decisions
MeetingDecisionOutcome
29 Mar 2012 Land between 16 & 18 Brabazon Road and 15 & 17 Johnson Road, HounslowThat planning permission for planning application 00139/D/P1 for the development of the site within the Brabazon Esta... Approved Open
29 Mar 2012 3 Devonshire Road, ChiswickThat planning permission for planning application 00355/3/P1 for the change of use from A1 (retail) to A3 (restaurant... Approved Open
29 Mar 2012 Garage Block, Lateward Road, Brentforda) That planning permission for planning application 00681/ADJ12/P1 for the demolition of existing garage blocks and ... Approved Open
29 Mar 2012 Land rear of 2 & 3 De Havilland Road and land adjacent to 12 & 14 Cobham Road, HounslowThat planning permission for planning application 00340/B/P1 for the development of the site to provide 10 x 2 storey... Approved Open
29 Mar 2012 Brentford Football Club, Griffin Park, Braemar Road, BrentfordThat planning permission for planning application 00143/A/P50 for the extension of time for implementation of extant ... Agreed Open