Resolved : i) That the new Section 106 £25,000 Greenham Park House contribution be noted. ii) That the Scheme 265, £2,000 FAR/Zenithproject contribution be noted, for use for training and education purposes within the Feltham Regeneration Area, specifically for use on the Butts Farm Estate Education Project. iii) That a range of improvements at Bedfont Lakes totalling £43,322 be agreed for improvements, deriving from Scheme 60 £20,000,Scheme 81 £15,000, 258 £8,322 ; (CIP to consult with Local Ward Councillors in Feltham North, and local ward PC with regard to improvement works in Feltham Park). iv) That scheme 278 £10,000 Challenge Road/ Shield Road be deferred, pending consultation with the Bedfont Lake Trust.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Summary To inform Members of recently received S106 contributions and recently signed agreements where the money has not yet been received, and to agree a number of S106 allocations.
1.0RECOMMENDATION 1) That Members note the new Section 106 agreement referred to in Section 2, paragraphs 2.1 – 2.2 of this report, and note the newly signed agreement(s) within section 3.
2) That Members agree the allocation of contributions from a number of S106 schemes as set out in section 4 of the report.
2.0RECENTLY RECEIVED CONTRIBUTIONS 2.1 There has been 1 contribution received of £25,000 since the last report to the Area Committee in December. It is recommended that the allocations be made in accordance with the terms of the legal agreements as follows:
2.2Land at Greenham Park House, (Phase 2) Chertsey Road, Feltham A contribution of £25,000 was received on 12 December 2007 towards local environmental improvements (which may for the avoidance of doubt include the provision of improvements to bus services and/or infrastructure and/or information and/or comprehensive Project Area 1.)
3.0SECTION 106 AGREEMENTS SIGNED SINCE DECEMBER 3.1 There has been 1 new agreements signed, for which contributions have not yet been received, since the last S106 monitoring report to the Area Committee.
3.2Hertz Rent A Car, Central Way, North Feltham Trading Estate, Feltham The agreement relates to the demolition of the existing building and erection of three new buildings and associated parking and landscaping with flexible permission for use as a motor vehicle hire centre (sui generis) and B1(c), B2 and B8 uses with ancillary office space for Unit A (occupying the southern part of site) and B1(c), B2 and B8 uses with ancillary office space for Units B and C (occupying the centre and northern part of the site). The obligations are: • Job Brokering Contribution of £16,635 towards the development of appropriate training and/or brokerage programmes to enable local people to gain the requisite skills to access or aspire to new job opportunities such as those presented by the development. • Construction and Training Strategy. • Notice of commencement. The training contribution, when received, will be reported to the Area Committee for noting, but as corporate monies, allocations are determined by the Executive. 4.0 S106 PROGRESS UPDATE 4.1 Members will be aware of the progress on various schemes that was reported to the July Area Committee, following identification and suggestion of appropriate projects by the West Area Committee, for allocations of uncommitted s106 contributions to be agreed with the Area Committee. Where a scheme has been allocated then further reports on progress on the implementation side can be prepared for the committee as required.
4.2The progress helps reduce the level of uncommitted s106 monies for the Area, and work continues on the outstanding amounts, and on new agreements such as those reported above, with continued monitoring reports to the Area Committee. Additionally, allocations are made from time-to-time based on reports from spending departments, incorporating the Director of Planning comments, and then agreed by the Area Committee.
4.3Since the July report, a number of schemes have been further worked up and are set out in the table below. These take account of Member comments and discussion, and liaison with the relevant spending departments.
4.4The table below outlines the proposals and costings, and where necessary refers to further information on the schemes and proposals.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.