The Executive agreed the recommendations of the report as follows: The Executive agreed to enter into a lease for the management and operation of the park with the Chiswick House and Gardens Trust for a period of 99 years and to delegate the finalisation of the terms to the Director of Environment in consultation with the Borough Solicitor and Lead Member. The Executive agreed to commence payments of £219,000 annually to the Chiswick House and Gardens Trust as set out in the draft lease and management agreement. The Executive agreed to novate the existing contracts that relate to the operation of the Gardens to Chiswick House and Gardens Trust.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
The gardens of Chiswick House (the Gardens) are owned and maintained by the Council. Chiswick House (the House) is owned by the Secretary of State for Culture, Media and Sport and managed by English Heritage.
In 2008 the Council was jointly awarded £7.6 million in association with English Heritage to renovate the House and Gardens of Chiswick House. This grant award was based on a detailed joint submission setting out the plans and arrangements for the development in two distinct phases. In the first phase the Garden and House would be completely renovated including the construction of a new café in the Garden (the Project). Under the second phase, the House and Gardens would be leased to a new trust, the Chiswick House and Gardens Trust (the Trust), established to maintain the Gardens and to manage and promote the House and Gardens. Phase 1 of the Project is nearing completion and has transformed the park. The Project has been managed by English Heritage on our behalf and on completion the House and Gardens are to transfer to the Chiswick House and Gardens Trust for a period of 99 years
Drafts of the lease and management agreement formed part of the Grant Agreement as defined below and this report seeks the Executives approval to enter into 1) a lease of the Gardens and 2)the integrated management agreement in respect of Chiswick House and Gardens Trust and to delegate the finalization of the terms to the Director of Environment in consultation with the Borough Solicitor and the Lead Member.
Recommendations
It is recommended that the Executive agrees to:
1.1Enter into a lease for the management and operation of the park with the Chiswick House and Gardens Trust for a period of 99 years and to delegate the finalisation of the terms to the Director of Environment in consultation with the Borough Solicitor and the Lead Member.
1.2Commence payments of £219,000 annually to the Chiswick House and Gardens Trust as set out in the draft lease and management agreement.
1.3Novate the existing contracts that relate to the operation of the Gardens to Chiswick House and Gardens Trust. 2. Background
2.1The Council entered into a Grant Agreement with the National Heritage Memorial Fund (Heritage Lottery Fund), English Heritage and Chiswick House and Gardens Trust (the Trust) on the 16th April 2008 (the Grant Agreement). This agreement set out the terms of the award of grant funding totaling £7,619,000 and incorporated the submission proposals including the leasing of the Grounds to Chiswick House and Gardens Trust on completion of the restoration project. The works are due to be completed in April 2010.
2.2An Agency Agreement Deed between the Council and English Heritage was signed on April 17th 2008. This agreement set out the arrangements under which English Heritage would undertake the restoration work on behalf of the Council under phase 1 of the project. Under the agreements, The financial risk of completing the works in the Gardens and the House to the standards required under the funding lies with English Heritage.
2.3The restoration project under phase 1 is now nearing successful completion and it is necessary to finalise the lease of the Gardens to theTrust
3. Terms of the Transfer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local Development Scheme (ENV 050)The recommendations of the report were agreed. The Executive agreed the recommendations of the report as follows: The...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.