Resolved (a) That the forthcoming public consultation on the West London Waste Plan be noted. (b) That the areas of potential concern of the Authority with respect to the proposed policies as set out in the report be noted. (c) That the Director submit a draft Authority response in consultation with Authority members for retrospective approval by the Authority at its next meeting.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report of the Director and Chief Technical Advisor 28 January 2011
West London Waste Plan: Authority Response to Public Consultation
SUMMARY This report provides the Authority with details of the forthcoming public consultation on the West London Waste Plan. It highlights issues for consideration in preparing the Authority’s detailed response.
RECOMMENDATION(S) The Authority is asked to:-
1) Note the forthcoming public consultation on the West London Waste Plan
2) Note the areas of potential concern of the Authority with respect to the proposed policies.
3) Instruct the Director to submit a draft Authority response in consultation with Authority members for retrospective approval by the Authority at its next meeting.
1. Introduction – It is important that the Authority takes an active role in influencing the development of national and regional waste management policy and regulations. Therefore the Authority should take the opportunity to respond to all requests for consultation.
2. Background – The Authority has received a number of updates on the development of the West London Waste Plan (WLWP). In April 2009 the Authority submitted its comments on the first round of public consultation. At its meeting in December 2009 the Authority expressed its concern at the slippage in the timetable for adoption of the WLWP, and the potential consequences that this could have to the Authority’s procurement process.
3. The Director of the Authority sits as an observer on the WLWP steering group.
4. Purpose of West London Waste Plan (WLWP) - The plan sets out the planning strategy up to 2026 for sustainable waste management in the Authority area to deliver national and regional targets for waste recycling, composting and recovery of waste by providing sufficient land capacity to manage waste arisings. Planning applications for any new waste management facilities (including those proposed by the Authority and its contractors) will be considered in accordance with the WLWP policies and they will also be assessed by the relevant host council against that council’s local development framework, including its local development management policies and any other material considerations.
5. Quantity of Waste to be managed – The WLWP is required to make provision for sufficient waste management capacity for all waste arisings, not just municipal waste handled by local authorities. The total level of waste arisings are taken from the Mayor of London’s London Plan and from this an estimated land take requirement for West London’s apportionment of London’s total waste stream has been estimated to be 56 hectares under the 2008 London Plan. This requirement has been reduced to far more realistic figure of 37 hectares as a result of the Mayor’s “minor alterations-waste arisings in apportionments” to the London Plan published in December 2009. There is therefore within the draft WLWP a contingency that will allow significant scope for a number of sites to be deleted from the draft WLWP proposed sites and policy documents should there be valid objections during the consultation stage, and particularly given that the revised London Plan figures will gain more weight following extended examination in public.
6. Public consultation – The draft WLWP has been signed off by the cabinet/executive of the six constituent boroughs. There is now a requirement for the draft plan to undergo a six week period of public consultation. The overall format for the consultation is proscribed by the Town and Country Planning Act, and it is understood that the consultation will commence on the 9th February and conclude on the 25th March 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.