That the Committee: · noted the contents of this report; · gave approval to officers to advertise a Cycle Tracks Order in relation to formalising the use of cycles on existing footpaths in the vicinity of the Civic Centre, as set out in proposals 1 (b), 2 and 3 (a), summarised in 4.1; · gave approval to officers to implement proposals in regards to converting footpaths to Cycle Tracks, as set out in 4.1 in the event that no objections are received, or objections are received and resolved or withdrawn, to the Cycle Tracks Order; · requested officers to provide an update to Committee setting out options for progressing the proposals in the event that objections remain; · gave approval in principle for a scheme to be developed by officers to facilitate cycle access across the entrance to the multi-storey car park (as set out in proposal 4b), with final approval delegated to the chair of the Area Committee, in consultation with the Lead Member for Performance and Customer Care; and · gave approval to officers to implement all further proposals, as set out in 4.2, table 2, namely to build new permissive paths in the vicinity of the Civic Centre and Lampton Park, to formalise the use of cycles within the park and to introduce improved signage in the area.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
This report sets out the proposal to upgrade paths in the vicinity of the Civic Centre and around Lampton Park so they are suitable for use by cyclists, pedestrians and mobility impaired people.
Recommendations
That the Committee:
1.1Notes the contents of this report.
1.2Gives approval to officers to advertise a Cycle Tracks Order in relation to formalising the use of cycles on existing footpaths in the vicinity of the Civic Centre, as set out in proposals 1 (b), 2 and 3 (a), summarised in 4.1.
1.3In the event that no objections are received, or objections are received and resolved or withdrawn, to the Cycle Tracks Order, gives approval to officers to implement proposals in regards to converting footpaths to Cycle Tracks, as set out in 4.1.
1.4In the event that objections remain, requests officers to provide an update to Committee setting out options for progressing the proposals.
1.5Gives approval in principle for a scheme to be developed by officers to facilitate cycle access across the entrance to the multi-storey car park (as set out in proposal 4b), with final approval delegated to the chair of the Area Committee, in consultation with the Lead Member for Performance and Customer Care.
1.6Gives approval to officers to implement all further proposals, as set out in 4.2, table 2, namely to build new permissive paths in the vicinity of the Civic Centre and Lampton Park, to formalise the use of cycles within the park and to introduce improved signage in the area.
Background
2.1Funding allocated within our newly approved Transport Strategy (Local Implementation Plan 2011-2031) provides for improvements to be made to parks and open spaces in order to create a network of safe, secure and attractive walking and cycle routes.
2.2In practice, this funding is used to upgrade (resurface, widen or otherwise improve) paths and tracks across parks and green spaces, reducing barriers to use by pedestrians, cyclists and mobility impaired people (those in wheelchairs or with buggies etc).
2.3The Council has committed to promoting walking and cycling as a form of transport – for environmental and health reasons, alongside a policy commitment (through our LIP) to encourage people to travel by non-car methods in order to reduce congestion, 1 improve air quality and reduce carbon emissions from transport. An increase in patronage within the park and surrounds could also increase the perception of safety, and in turn increase usage, creating a virtuous cycle.
2.4The project is part of the proposed west London wide ‘greenways network’ which would link parks and open spaces across the west of the capital through a comprehensive network of pathways. As part of this programme we recently completed similar projects in Cranford & Avenue Park, across Hounslow Heath, in Crane Park (see Figure 1 below) and shortly within Hanworth Park.
Figure 1 – Recently completed Greenway in Crane Park, Hanworth
2.5It is intended that the upgraded paths around the Civic Centre and Lampton Park would provide an improvement for leisure and recreational walkers and cyclists accessing and using the area. In addition, the improvements will also facilitate sustainable access to the council’s offices, Lampton School, Lampton Sports Centre and will further function as a traffic-free route between the Great West Road and Hounslow Town Centre. Figure 2 summarises in outline the proposed route and improvements, which were consulted on in January/February 2012. The detailed project proposal now being presented to members, following consultation, is summarised in Section 4 of this report.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.