Resolved - (a) That the current financial position (as set out in appendix 1 of the report) which showed an underspend of £1.8 million be noted. (b) That performance to date measured against the Key Performance Indicators for 2013/2014 (as set out in appendix 2 of the report) be noted. (c) That the current position of reserves be noted. (d) That progress on implementing Finance, HR and ICT systems and infrastructure be noted.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
SUMMARY This report provides an update on the financial position of the Authority at the end of period 8.
RECOMMENDATION(S) The Authority is asked to:-
1) Note the current financial position which shows an under spend of £1.8M (Appendix 1)
2) Note the Key Performance Indicators for 2013-14 to date (Appendix 2)
3) Note the current position of reserves
4) Note progress with the implementation of Finance, HR and ICT systems/infrastructure.
1. Expenditure 2013-14. The current revenue forecast for the Fixed Cost Levy (Appendix 1) is for an under spend of £1.8 M, mainly due to the decrease in waste transport and disposal costs. During the eight months of this year, cumulative residual and organic/recycling waste tonnages at the HRRC sites were 6,700 and 1,400 respectively below the same period last year. It is anticipated that the full procurement budget will not be required but this potential under spend might be offset by the outstanding issues described below. 2. Following the transfer of Victoria Road and Transport Avenue sites to SITA UK Limited, WLWA will no longer hold any stock. The stock has been transferred following negotiations to achieve the best possible price from SITA UK Limited. The balance will be written off at the end of the financial year.
3. The pension scheme was scheduled for revaluation at 1 April 2013 and the Authority is anticipating increased costs as a result. Provision in 2013/14 budget was made but the full effect on WLWA will only be known after pension actuaries and LPFA provide more detail before the end of 2013/14 financial year.
4. Procurement contract. In December West London Residual Waste Services Contract was signed. 50 staff from Victoria Road and Transport Avenue sites were transferred under TUPE arrangements to SITA UK Limited. The interim services started from 19 January 2014.
5. Key Performance Indicators. The latest performance indicators for the period to 31 December 2013 show that the Authority is continuing to perform well against its targets for the current financial year. In particular both overtime and sickness rates have been significantly reduced. 6. Reserves – the Treasurer indicated in June 2013 that a prudent level of reserves would be 5% of budgeted expenditure. The target based on 2013-14 expenditure was £3M. The current level of under spend indicates that the level of reserves at 31 March 2014 is likely to be in the region of £4M. The Authority has a historic loan of £2.9M with the London Borough of Harrow on which interest at 5.2% is currently paid. The Treasurer is proposing to repay a proportion of this loan, using reserves at the end of the financial year.
7. Finance, HR systems and ICT Infrastructure. A formal project team has now been formed with Ealing to ensure the successful delivery of the new HR and Finance systems for use from 1 April 2014. The ICT infrastructure may not be in place until late April due to lead in times for the installation of new broadband/communication lines with Ealing.
8. Financial Implications – These are detailed in the report.
9. Legal Implications – There are no legal implications as a result of this report.
10. Impact on Joint Waste Management Strategy – Improvements to financial management in the Authority will continue to ensure that it achieves value for money. Policy 7: The West London Waste Authority and constituent Boroughs will seek to provide waste management services that offer good value, that provide customer satisfaction and that meet and exceed legislative requirements.
Policy 8: The West London Waste Authority and constituent Boroughs will work together to achieve the aims of this strategy and are committed to share equitably the costs and rewards of achieving its aims.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.