Staines Road / Grovestile Waye - Junction Improvements

Approved Committee 2 papers

Bedfont, Feltham, Hanworth Area Forum approved this item on Thursday 13 March 2014. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

Resolved – Members approved: Implementation of new traffic islands and kerb line realignment works on the A315 Staines Road, at the junction with Grovestile Waye . To provide safer crossing facilities for pedestrians and to slow vehicle speeds through the roundabout. Authorisation of officers, where possible, to resolve any objections received to the statutory consultation and implement the scheme and, in the event of any objections remaining unresolved, that the Chair of the Forum be given delegated authority to determine these objections in consultation with the ward councillors.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Bedfont, Feltham, Hanworth Area Forum

Report for: ACTION

Contains Confidential No or Exempt Information

Title Staines Road / Grovestile Waye – Junction Improvements Member Reporting Cllr Ed Mayne, Cabinet Member for Community Safety and Regulatory Services Contact Details Tom Sharland Transport Projects Officer Network Management Regeneration, Economic Development & Environment Department Tel: 020 8583 2270 Email: [email protected] For Consideration By Bedfont, Feltham, Hanworth Area Forum Date to be Considered 13 March 2014 Implementation Date if May/June 2014 Not Called In Affected Wards Bedfont Keywords/Index N/A

1. Details of Recommendations

That the Area Forum approve:

1.1Implementation of new traffic islands and kerb line realignment works on the A315 Staines Road, at the junction with Grovestile Waye. To provide safer crossing facilities for pedestrians and to slow vehicle speeds through the roundabout. 1.2 Authorises Officers, where possible, to resolve any objections received to the statutory consultation and implement the scheme and, in the event of any objections remaining unresolved, agrees that the Chair of the Forum be given delegated authority to determine these objections in consultation with the Ward Councillors.

If the recommendations are adopted, how will residents benefit? Spending Wisely – This scheme will be delivered in July 2014 partnership with Hounslow Highways. This provides time and cost efficiencies and will also ensure this scheme is aligned with planned Core Investment Period (CIP) carriageway resurfacing works. Quality of Life – Improved pedestrian facilities will July 2014 encourage residents to travel actively for everyday journeys. While addressing safety issues at this junction will decrease the risk of future accidents.

2. Report Summary

1. This report details the improvement to the junction of the A315 Staines Road and Grovestile Waye in Bedfont. The scheme will provide traffic islands, to assist pedestrians in crossing both roads and to slow vehicle speeds through the junction. 2. It recommends a total of three new traffic islands, two of which will provide informal pedestrian crossing points. Along with associated kerb line works to provide the necessary carriageway space for larger vehicles to use the junction effectively. The scheme will help deliver objectives detailed in the Local Implementation Plan (LIP), as approved by Borough Council on 31 January 2012. 3. These recommendations are being made because their were a total of five accidents at the junction between 2009 and 2012, the majority of which involved a vehicle turning right out of Grovestile Waye. A pedestrian survey, undertaken in July 2013, also showed nearly 300 people crossing Staines Road (to the east of Grovestile Waye) in a 12 hour period, primarily from the residential area to the south of Staines Road, to the eastbound bus stop. 4. If adopted, the key financial implications for the Council are to be funded by Transport for London (TfL) from the approved LIP budget. The cost estimated provided by Hounslow Highways is £43,143.78. The scheme is subject to a re-measure upon completion, which may alter this cost slightly. 5. An additional point to note is that Hounslow Highways are in the process of aligning carriageway resurfacing works for this section of Staines Road. This will reduce cost and future disruption through having to revisit the site a second time.

3. Reason for Decision and Options Considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
_Staines Road Grovestile Waye_Junction Upgrade PlanAppendix A 373 KB Download
PDF
Staines Road / Grovestile Waye: Junction ImprovementsReport 116 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Staines Road / Grovestile Waye - Junction ImprovementsThis decision
  2. 80 - 82 Staines RoadApproved
  3. Land south of Staines Road, north of Ascot Road and Clockhouse LaneApproved
  4. Falcon House, Staines RoadApproved
  5. Chongie Entertainment Ltd, Parts of Neals Corner, 1-5 Staines Road and 2-6 Bath Road, Hounslow, TW3 3HJ.Decided
  6. 379-389 Staines Road, HounslowApproved

More from Hounslow Bedfont, Feltham, Hanworth Area Forum

All decisions
MeetingDecisionOutcome
24 Feb 2022 Community Infrastructure Levy (CIL) & S106 Update - Presentation by Danalee EdmundThat training be provided for Members on CIL spend so that they could understand how Local CIL could be spent in thei... Decided Open
25 Nov 2021 Environmental Champions Programme - Presentation by Jess Prest & Nimesh Zaveri, Green Recovery OfficersMembers asked that the focus for engagement be on youth groups and the BAME community and that officers report back t... Decided Open
25 Nov 2021 Items for Future MeetingsIt was agreed that Councillor Samia Chaudhary would provide a presentation on Parks and Open Spaces and Leisure Servi... Agreed Open
28 Jan 2021 The Crane Valley Project - Presentation by Rob Gray, Chair of FORCEThat the report be noted and that the work being done on the project be commended. Noted Open
30 Jan 2020 Local Police Update - Sgt. James HuntleyThat Sgt. Huntley will provide Members with the current list of officers for each ward. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies