Resolved
Agreed.
Planning Committee agreed this item on Thursday 26 June 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed.
1.1The proposed development is for the erection of a 426 guestroom hotel, consisting of conferencing and meeting facilities, restaurant and bar, health club and swimming pool, extensive landscaping, parking and associated development.
1.2This scheme follows a previously approved scheme for a 318 bedroom hotel that expired in 2007. The current scheme is three storeys larger, with an additional 108 bedrooms, improved facilities and enhancements to the green belt.
1.3Whilst the site is not located within a town centre and would result in some development within the Green Belt, it is considered that the proximity of the site to Heathrow airport and the Bedfont Lakes office development and the economic regeneration benefits for the local area would outweigh any harm. Furthermore, the scheme is considered to be of a high design standard offering positive knock-on effects to the public accessibility of adjacent Green Belt land and improvements to pedestrian and cycle routes in the vicinity of the site.
1.3The application is recommended for approval subject to a section 106 agreement and referral to the Greater London Authority (Stage II)
2.0SITE DESCRIPTION
2.1The application site is situated between the western and south-western arms of Clockhouse Roundabout and is approximately 4.82ha in size. It is bounded to the north by the A30 Staines Road dual-carriageway, to the south by Clockhouse Lane, to the east by an Esso petrol filling station and to the west by Ascot Road, which leads to Ascot Road Industrial Estate.
2.2The surrounding area includes the „New Square‟ office development, Bedfont Lakes Country Park, Ascot Road Industrial Trading Estate and extensive areas of Green Belt, including Mayfield Farm to the north of Staines Road. The nearest residential properties are located on the western side of Clockhouse Roundabout (624 & 626 Staines Road).
2.3Remediation works to site have been undertaken in conjunction with a previous planning consent for a hotel development and included the excavation of contaminated landfill and the provision of a clean base over the construction zone (this is situated towards the north-east corner of the site).
2.4A significant portion of the site (western end) is designated as Green Belt; otherwise there are no other planning policy designations on the site. The Bedfont Green Conservation Area is located to the north-east of the site on the opposing side of the Clockhouse Roundabout. The A30 Staines Road and Clockhouse Roundabout are maintained by Transport for London (TfL). The site has a Public Transport Accessibility Level (PTAL) of 1, which is described as „Very Poor‟.1
3.0HISTORY
3.100287/J/P29 - Demolition of existing buildings, erection of a 15793m2 gross external (including basement plant) 318 bedroom hotel and associated uses on eastern part of site; restoration of Western part of site to form landscaped open space. Approved with legal agreement 17/01/2001
3.200287/J/P39 – Erection of a 4 storey hotel (408 guestrooms) with associated access, parking and landscaping. The application was presented at committee
1 PTAL uses a mathematical formula to demonstrate accessibility by public transport. The values of a site may range from 1 at the lower end of the scale to 6 at the higher. on the 28/02/2002 and was approved subject to the completion of a S106 Agreement. However the agreement was never completed.
3.300287/J/P40 - Variation of condition 2 (time limit) of original decision 00287/J/P29 dated 17/01/01 to extend to end January 17 2007. (Demolition of existing buildings, erection of a 318 bedroom hotel including basement plan and associated uses on eastern part of site restoration of western part of site to form landscape open space). Approved 25/06/2004
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Clockhouse mapPlan | 1 pages | Download |
PDF |
Land at Bedfont Lakes, Clockhouse Lane, BedfontReport | 21 pages | DownloadRead as text |
Follow Planning Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Aug 2026 | 80 - 82 Staines RoadResolved – that planning application P/2023/2705, erection of two apartment blocks of 3-5 storeys and 4-6 storeys to ... | Approved | Open |
| 11 Jun 2026 | 64E Waldeck Road, ChiswickResolved – that planning application P/2026/0264, erection of a single storey rear extension to the house, was approv... | Approved | Open |
| 5 Mar 2026 | Central Park EstateResolved – that planning application P/2024/4226, erection of four commercial units of mixed uses B2 (General Industr... | Approved | Open |
| 5 Feb 2026 | Block B, Brentford Lock WestResolved – that planning application P/2025/1313, erection of part 10, part 11 storey building comprising 124 residen... | Refused | Open |
| 5 Feb 2026 | 97 Devonshire RoadResolved – that planning application P/2025/0646 , erection of a rear roof extension with four front roof lights and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.