Resolved - a) That the potential impact of the HS2 rail link on the Victoria Road site and on its operations be noted. b) That the retrospective resolution of the Authority to oppose High Speed Rail (London - West Midlands) Bill be approved. c) That in the judgment of the West London Waste Authority it is expedient for the Authority to oppose the High Speed Rail (London – West Midlands) Bill introduced in the Session of Parliament 2013-14. d) That the Director take all necessary steps to carry the foregoing Resolution into effect, that the Common Seal be affixed to any necessary documents and that confirmation be given that Sharpe Pritchard (Parliamentary Agents) be authorised to sign the Petition of the Authority against the Bill.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report of the Director and Chief Technical Advisor 27 June 2014
Impact of HS2 rail link on Victoria Road Waste Transfer Station
SUMMARY This report provides an update on the potential impact of the HS2 rails link on the Authority’s site and operations at Victoria Road.
RECOMMENDATION(S) The Authority is asked to:-
1) Note the potential impact on the site and its operations
2) To approve the retrospective resolution of Authority to oppose High Speed Rail (London – West Midlands) Bill
3) That in the judgment of the [West London Waste Authority] it is expedient for the Authority to oppose the High Speed Rail (London – West Midlands) Bill introduced in the Session of Parliament 2013-14.
4) That the Director take all necessary steps to carry the foregoing Resolution into effect, that the Common Seal be affixed to any necessary documents and that confirmation be given that Sharpe Pritchard (Parliamentary Agents) be authorised to sign the Petition of the Council against the Bill.
1. Introduction – It is important that the Authority takes an active role in influencing the development, at national and regional level, waste management policy and regulation. Therefore the Authority should take the opportunity to respond to all appropriate consultation requests.
2. Background – Since December 2010 the Authority has received regular updates on the impact of the proposed HS2 rail link on the Victoria Road waste transfer station and household reuse and recycling centre (HRRC). The Authority will recall that the initial proposals for this rail link would have had a very significant impact on the Authority’s operations at this site. However, following dialogue and lobbying by others, HS2 decided to place the new rail link in a tunnel approximately 20m below the operating surface of the site. Whilst there could be potential impacts for future construction of buildings over the tunnel, it was agreed by the Authority and the current operators of the site, SITA UK Ltd, that any conditions relating to building over the tunnel would be manageable and would not prejudice the use of the site for the West London Residual Waste Services contract signed on 27th November 2013.
3. HS2 rail link - On the 16th October 2013, HS2 wrote to the Authority formally requesting contact details for affected parcel of lands along the route. The letter also identified a new parcel of land that will be affected along the north western corner of the Victoria Road site which had not been previously disclosed. On the 25th November 2013 HS2 sent a Notice to Owners, Lessees and Occupiers. This notice included a plan which shows an access route along the affected area of land identified in the letter on the 16 th October. The Authority has subsequently written to HS2 on the 6th December requesting a further information to understand the timing and potential impact of the access requirement. On the 6th February the Authority received a response from HS2 which indicated that the access route is required for diversion of a sewer beneath the adjacent London Underground Central Line. With no detail on the timing duration or nature of the works it is very difficult to evaluate the impact of this access requirement. A site meeting was arranged for Thursday 6th March. However, as a precaution, the Authority submitted an objection to the environmental statement for this area on this specific part of the proposal to the consultation on the Environmental statement for the hybrid bill.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.