CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
West London Waste Authority, Friday 19 September 2014 at 10.00am

Waste Prevention Annual Action Plan - Mid-year Review

Noted Committee 3 papers

West London Waste Authority noted this item on Friday 19 September 2014. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

Resolved - (a) That the success of waste minimisation plan activities in 2013/2014 be noted. (b) That the progress of waste minimisation activity so far in 2014/2015 be noted. (c) That the process to be followed to develop a plan for 2015/2016 and plan to integrate the waste prevention strategy into the Joint Municipal Waste Management Strategy be noted.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to West London Waste Authority, 3 pages

WEST LONDON WASTE AUTHORITY

Report of the Director and Chief Technical Advisor 19 September 2014

Waste Prevention – summary of 2013/14 activity and progress so far in 2014/15

SUMMARY This report provides an update on the delivery of projects in west London by the WLWA Waste Minimisation Team.

RECOMMENDATION(S) The Authority is asked to:-

1) Note the success of plan activities in 2013/14 (as at appendix 1)

2) Note the progress of activities so far in 2014/15 (as at appendix 2)

3) Note the process to be followed to develop a plan for 2015/16 and the plan to integrate the Waste Prevention Strategy in to the JMWMS

1. Introduction – In 2010 it was agreed that The Authority should take the lead role to deliver the campaigns agreed by the constituent boroughs in the Waste Prevention Strategy (2011 – 15) and yearly Waste Prevention Action Plans (WPAP). The Waste Minimisation (WM) Team delivers the campaigns which target the 5 key waste streams of food, textiles, waste electrical and electronic equipment, furniture and nappies. The WM Team is also now responsible for the Authority’s website, intranet, social media, and media communications.

2. Background – The WPAP for 2014/15 was agreed at the Authority meeting on 13 th December 2013 and the final activities within the key projects agreed with the constituent boroughs in the following months. Each quarter the progress against actions in the plan are reported to the constituent boroughs and then published on the Authority’s website.

3. Performance against the 2013/14 WPAP – The detailed results at shown in appendix to this report. There were 22 actions in the 2013/14 plan, at the end of the year 16 achieved green status, 5 were amber and 1 action, Fo5, was red. The home composting support work (Fo5) was not completed, as the year progressed the constituent boroughs decided that it wasn’t a priority and staff resources were diverted toward promoting Love Food Hate Waste. A green status was given when the targets published for an action were met. A few successes to highlight are described next.

4. The partnership working with the School Food Trust for the Let’s Get Cooking Clubs (Fo1), our positive relationship with them enabled us to take the messages more widely than just the participants in the clubs and the learning has been used to form the basis of waste prevention work with other local authorities including the Merseyside Recycling and Waste Authority ‘Waste Munchers’ programme. 5. Work with schools to help them reduce their food waste (Fo2) saw one school reduce the number of food items thrown away by 15%. Results across all schools were varied but show there is significant scope for schools to reduce waste saving themselves a lot of money and at the same time involving their pupils in healthy eating and positive environmental messages

6. A new website was developed for the Hounslow Furniture Project (Fu1) to help local residents find out about this service which accepts furniture from homes that no longer need it and provides good quality furniture to people who don’t have cash to spare for brand new furniture. Since the launch of the site it receives a regular flow of new visitors who can find more useful information than was previously available online.

7. The number of people spoken to and the events attended to promote washable nappies (N1) far exceeded the target. There was been a very positive response from both residents and local organisations to the availability of unbiased information.

8. The WM Team attended 151 events and spoke to 5,612 people during the year. Action C3 saw residents questions about reducing, re-using, repairing answered and people have begun actively seeking out our information including event organisers who are now inviting us to attend free events and groups inviting us to talk.

9. The Authority’s online reach is increasing with more people visiting the website, signing up to the monthly newsletters and an increased following on social media.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waste Prevention Annual Action Plan: Appendix 1Appendix 15 pages Download
PDF
Waste Prevention Annual Action Plan: Appendix 2Appendix 13 pages Download
PDF
Waste Prevention Annual Action Plan: Mid-year ReviewReport 3 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Waste Prevention Annual Action Plan - Mid-year ReviewThis decision
  2. Update on the Waste Prevention Action Plan for 2014/15 and proposed 2015/16 Action PlanNoted
  3. Waste Prevention Plan 2012-13Noted

More from Hounslow West London Waste Authority

All decisions
MeetingDecisionOutcome
18 Mar 2016 Budget Monitoring Report Period 10 (January)Resolved - (a) That the current financial position in 2015/2016 to Period 10 and Key Performance Indicators be noted.... Noted Open
18 Mar 2016 Annual Procurement PlanResolved - (a) That the Annual Procurement Plan for 2016/2017 be approved. (b) That that the Authority’s contract reg... Approved Open
18 Mar 2016 Corporate GovernanceResolved - (a) That the business plan for 2016/2019 set out in appendix 1 be approved. (b) That the arrangements for ... Approved Open
18 Mar 2016 Exclusion of Press and PublicResolved - That the public and press be asked to leave the meeting during discussion of the following item because ex... Decided Open
29 Jan 2016 Budget Monitoring Report Period 8 (November)Resolved - a) That the current financial position in 2015/16 to Period 8 and Key Performance Indicators be noted. b) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies