Overview and Scrutiny Committee, Wednesday 17 December 2014 at 7.00pm

Monitoring information - decisions taken under urgency arrangements

Noted Scrutiny 1 paper

Overview and Scrutiny Committee noted this item on Wednesday 17 December 2014. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

Resolved - (a) That the guidance on the use of the urgency procedures be noted. (b) That the instance of the uses of the urgency procedure since the last report to the Committee be noted.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Overview and Scrutiny Committee, 4 pages

Report for: INFORMATION

Contains Confidential No or Exempt Information Title Monitoring Information – Decisions taken under urgency arrangements Member Reporting Cllr John Chatt, Chair Overview & Scrutiny Committee (OSC) Contact Details Ian Duke, Head of Policy & Scrutiny 020 8583 2191; [email protected] For Consideration By Overview & Scrutiny Committee Date to be Considered Wednesday 17 December 2014 Implementation Date if N/A Not Called In Affected Wards All Keywords/Index scrutiny, urgency

1. DETAILS OF RECOMMENDATIONS

Members are asked to:

1. Note the guidance on the use of the urgency procedures 2. Note the instance of the uses of the urgency procedure since the last report to OSC.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Non applicable

2. REPORT SUMMARY

In 2013/14 the Overview and Scrutiny Committee (OSC) re-established a standing item to be included at all meetings to update the committee on urgency decisions that the Chair had been notified of, or asked to agree urgency upon.

There have been two decisions taken under urgency since the last report to the meeting on 17 September. A summary of each, plus links to key documents, is set out below. 3. BACKGROUND

3.1The council’s constitution provides for key and executive decisions to be taken as a matter of urgency when there is a danger of the Authority finding its position prejudiced if a decision is not taken. These powers are utilised by officers with the agreement of the appropriate councillor.

3.2There are four circumstances set out below where the normal processes for advance public notice that a Cabinet decision is to be made are curtailed, or there is not an opportunity to call in a Cabinet decision. In each case there is a prescribed process set out in the constitution for engaging with Scrutiny and publishing the grounds for urgency.

3.3The four circumstances are where:

It is not practical to comply with the requirement that 28 days notice should be given that a Cabinet decision will be taken in private. It is not practical to comply with the requirement that 28 days notice should be given (in the Forward Plan) that a Key Decision is to be taken by Cabinet. It is not practical to convene a quorate meeting of the full Council to take a Cabinet decision which is contrary to the Budget or Policy Framework. Where any delay likely to be caused by the call-in process would seriously prejudice the council’s or the public’s interests or could lead to an (increased) risk of damage to people or property.

4. DECISIONS TAKEN SINCE FEBRUARY 2014

4.1The following are Council and Cabinet Decisions Taken under Urgency Arrangements where the Chair of OSC has been notified, or agreed that the decision cannot reasonably be deferred:

4.2REG 247 Lift replacements – Brentford Towers and Hunter and Belvedere House (16 October 2014) – link to decision

This Single Member Decision was to approve the award of the contract for the modernisation of the lifts ar Brentford Towers and Hunter and Belvedere House to Lift Specialists Ltd for the sum of £957,720.

The reason for urgency was that although 28 days advance publication was given, the entry stated that the award of the contract would be by Hounslow Homes. Following the decision by Cabinet on 13 October 2014 to bring the housing management service back in house, any award needed to be made by Hounslow Council. As advanced notice had been given for the decision, and given the expectations of residents, it was decided it would be disproportionate to wait a further 28 days before the decision was made.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Monitoring information: decisions taken under urgency arrangementsDecisions 4 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. Monitoring information - decisions taken under urgency arrangementsThis decision
  2. Monitoring information - decisions taken under urgency arrangementsDecided
  3. S106 Monitoring Update Report - Information ItemNoted

More from Hounslow Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
26 Mar 2026 Joint Health Overview and Scrutiny Committee UpdateThat the update was noted. Noted Open
26 Mar 2026 Work Programme Review - suggestions for 2026/27That the suggested topics would be noted for consideration by the incoming Committee as part of its work programming ... Noted Open
26 Mar 2026 Forward Plan ReviewThat the forward plan was noted. Noted Open
26 Jan 2026 Forward Plan ReviewThat the Forward Plan was noted. Noted Open
26 Jan 2026 Work Programme ReviewThat the Work Programme was noted. Noted Open