CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Hounslow
Brentford and Syon Area Forum, Thursday 15 January 2015 at 7.30pm

Brentford Creek Environmental Improvement Works

Noted Committee 1 paper

Brentford and Syon Area Forum noted this item on Thursday 15 January 2015. Below is the council's own wording, with the papers it was decided on.

Item59

Resolved

Members noted the contents of this report and by majority vote agreed that: a) The environmental improvements at Brentford Creek, as detailed in the design “Brentford Creek, General Agreement” shown in paragraph 3.2 of the submitted report be approved in principle, subject to a review by Syon ward councillors in consultation with officers to ensure that the proposals were integrated with the proposed development at Land South of the High Street, Brentford; b) The decision to approve the proposals should be delegated to the Chair in consultation with Syon ward councillors and the relevant chief officer. 9.55pm – Councillor Sampson proposed the suspension of Standing Orders in order to complete the business on the agenda, which was supported by all members present.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Brentford and Syon Area Forum

Report for: ACTION

Contains Confidential No or Exempt Information Title Brentford Creek – Thames Path improvements Member Reporting Councillor Mann, deputy leader. Contact Details Kieran Taylor, Principal Transport Planner. 020 8583 5206, [email protected] For Consideration By Isleworth & Brentford Area Forum Date to be Considered 15 January 2015 Implementation Date if 15 January 2015 Not Called In Affected Wards Syon Ward Keywords/Index Thames path, S106 1. Details of Recommendations

The Isleworth & Brentford Area Forum is asked to agree to note the contents of this report and either: a) Approve the environmental improvements at Brentford Creek, as detailed in the design “Brentford Creek, General Arrangement” shown in paragraph 3.2, or b) Instruct officers to undertake a new consultation on the improvements and delegate the decision to approve them to the chair, in consultation with ward councillors.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Residents will benefit by having an improved public Autumn 2015 realm on the Brentford waterfront. This helps deliver the Council promise to continue investing in our roads and pavements – Corporate Plan 2014-19.

2. Report Summary 1. This report deals with improving the Thames Path to the south and east of the Heidelberg building. 2. It recommends that members either approve the project or instruct officers to undertake another consultation. 3. These recommendations are being made because they support the aims of the local plan (currently under examination by the planning inspectorate) to regenerate Brentford town centre as a vibrant District Centre that celebrates the town’s heritage and waterside location. 4. If adopted, the key financial implications for the Council are a capital spend of £209,397 and a 23 year maintenance cost (paid as a lump sum) of £61,212. The scheme will be funded from S106 contributions (40k) and LIP funding (230k) received from Transport for London (TfL). 3. Reason for Decision and Options Considered

3.1Plans to improve the Thames Path by Brentford Creek were first brought to the Isleworth & Brentford Area Committee (monitoring) on 2 September 2010. The path to the south and west of the Heidelberg building is adopted highway, under the control of the Council, and maintained by Hounslow Highways. The scope of the project area is shown below.

Heidelberg Building

Scope of works

3.2The path is currently in a poor state of repair and is need of investment to make it welcoming and attractive. The key proposals are to: improve the paved surface with regular block paving introduce new shrub planting improve the guardrail at the water’s edge.

Indicitative example of new guardrailing and paving 4. Key Implications

4.1The measure of success will be the physical improvement of the public realm and its ongoing maintenance to a high standard. Implementation will be complete by Autumn 2015.

5. Financial Details

a) Financial Impact On The Budget

There will be no impact on The Budget as funding for this scheme will come from developer S106 contributions and LIP funding received from TfL.

b) Financial Background

S106 funding has been allocated to environmental improvements at Brentford Creek from; scheme 108 (£10,000) approved by IBAF on 18 July 2013, and scheme 197 £30,104. The developer agreed to re-allocate these funds towards Brentford Creek on 10/05/11/. A Cabinet Member Single Member Decision to allocate funds from scheme 197 is anticipated to be taken in late January 2015.

£77,600 of funding from the LIP capital programme has been allocated to this scheme. £153,000 of funding from the LIP Greenways programme has been allocated to this scheme

c) Comments of the Assistant Director Strategic Finance

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Brentford Creek Environmental Improvement WorksReport 474 KB DownloadRead as text

More from Hounslow Brentford and Syon Area Forum

All decisions
MeetingDecisionOutcome
10 Feb 2022 Open ForumIt was agreed that responses would be provided outside this meeting. (see supplementary agenda published for referenc... Agreed Open
5 Feb 2020 Budget 2020-21 presentation - Councillor Shantanu RajawatResolved : The Budget Presentation 2020-21 was noted. Noted Open
5 Feb 2020 Forming the Community Safety Strategy 2020-2023 - Permjit Chadha and Dorita Diaz (LBH)Resolved : · The Area Forum noted the submitted presentation and the resulting discussion. · Members encouraged resid... Noted Open
5 Feb 2020 Petitions UpdateResolved : Members noted the submitted petitions and the discussions at the meeting. Noted Open
17 Oct 2019 Conservation Area Appraisals (information item)Resolved : The Area Forum noted the submitted briefing on the current round of area appraisals consultation and comme... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies