Resolved – a) That the Fixed Cost Levy for 2015/16 of £11.279 million as set out in section 12 of the report be agreed. b) That the Pay As You Throw (PAYT) charges set out in section 11 of the report be agreed and officers be granted delegated authority to revise rates during the year should the market change or anticipated rises are higher than the budget where fixed rates are not in place. c) That the trade waste prices for 2015/16 as set out in section 13 of the report be agreed. d) That the capital budget set out in section 14 of the report be agreed. e) That the level of reserves to avoid the risk of supplementary levies as set out in section 15 of the report be agreed.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
2.1The total cost for 2015/16 is budgeted to be £62.0 million, an increase of £5.3 million from £56.7 million 2014/15 budget.
2.2The two most significant items making up this movement are: • The cost of waste transport and disposal – the 2015/16 budget is £56.7 million which represents an increase of £7.3 million from the 2014/15 level. The four components of this growth are the low waste tonnage forecast by boroughs for 2014/15, the end of a contract with a supplier where we enjoyed exceptionally competitive rates, an increase in landfill tax and contract inflation. This growth is based on waste tonnage and therefore is primarily seen in an increase in PAYT charge for 2015/16. • Financing and other costs – the Authority borrows money from 4 boroughs to finance capital contributions used in the construction of the West London Residual Waste Services (WLRWS) energy from waste (EfW) plant. The resulting interest charge is added to the debt and no cash payments will actually be made in 2015/16 – it is deferred and as planned will be paid following the completion of the EfW plant. Therefore the 2015/16 budget removes the financing cost of £1.9 million so that boroughs will not be charged through the Fixed Cost Levy. 2.3 Both of these are detailed later in this report. 2.4 The 2015/16 capital requirement totals £0.7 million, a reduction of £0.4 million from 2014/15. New site equipment, site improvements and a replacement waste data management system make up this total.
3. Expenditure and Income
3.1The table below sets out the 2015/16 budget and the movement from the 2014/15 budget. The latest 2014/15 forecast is also included to provide context and illustrate the current level of activity. The budget headings are per the standard CIPFA classifications. 2014/15 2014/15 2015/16 Change in budget forecast budget budgets £’000 £’000 £’000 £’000 Costs Waste Transport & 49,389 52,889 56,743 7,354 Disposal Financing & Other* 1,925 0 0 (1,925) Premises 1,762 2,152 2,369 607 Supplies & Services 1,445 1,131 906 (539) Depreciation 548 349 409 (139) Employees 1,607 1,686 1,548 (59) Total costs 56,676 58,207 61,975 5,299
Income PAYT Levy Income 42,411 45,967 49,067 6,656 FCL Levy Income 11,944 11,944 11,280 664 Other income 2,321 1,701 1,628 (693) Total income 56,676 59,612 61,975 5,299
Net cost/income 0 1,405 0 0 * includes £1 million contingency 14/15
Commentary for each budget heading follows:
4. Waste Transport & Disposal (WTD)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.