Affordable Housing Committee, Thursday 5 March 2015 at 5.00pm

Mayor's Housing Covenant

Decided Committee 1 paper

Affordable Housing Committee decided this item on Thursday 5 March 2015. Below is the council's own wording, with the papers it was decided on.

Item30

Resolved

... view the full minutes text for item 30.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Affordable Housing Committee

Report for: ACTION / INFORMATION

Contains Confidential or Exempt Information

Title REG264: Mayor’s Housing Covenant 2015 – 2018: Approval to allocate funding for feasibility assessments Member Reporting Councillor Steve Curran, Cabinet Member Housing Contact Details [email protected] For Consideration By Affordable Housing Committee Date to be Considered 5 March 2015 Implementation Date if 17 March 2015 Not Called In Affected Wards All Keywords/Index Affordable housing, HRA, GLA grant Mayor’s Housing Covenant

1. Details of Recommendations

The Affordable Housing Committee is asked:

1. To note Affordable Housing & Supply Services successfully secured grant contribution from the GLA to deliver 124 units of new council homes before March 2018.

2. To approve the allocation of initial budget of £750k from resources identified within the approved HRA business plan to establish indicative schemes and costs for the remainder of Phase 1.

3. To delegate authority to the Assistant Director for Housing to approve the commencement of procurement and to award the contract for the appointment of professional advisors to establish a short-list of indicative schemes and costs for the remainder of Phase 1 subject to the tender return not exceeding the initial budget of £750k.

4. To delegate authority to the Assistant Director for Housing subject to him reporting back to the Affordable Housing Committee for further funding approval to accept and award a contract for the full appointment of professional advisors to complete the detailed delivery of shortlisted schemes. If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference The delivery of new affordable homes will contribute March 2018 towards meeting the housing needs of Hounslow residents.

2. Report Summary

1. This report seeks authorisation to conduct two separate procurement exercises to appoint professional advisors. The first to establish a short-list of indicative schemes and costs for the remainder of Phase 1. The second to progress procurement and report back to Affordable Housing Committee for further funding to accept and award full appointment of professional advisors to complete detailed delivery of the short-listed schemes.

2. This report recommends use of Housing Revenue Account (HRA) resources to allocate an initial budget of £750k to fund the preparation of design options and feasibility assessments and authority to progress procurement in order to report back to Affordable Housing Committee.

3. These recommendations are being made in order to enable the Council to create a short-list of schemes and deliver new affordable homes for Hounslow residents within the timescales required by the GLA as a condition of grant funding.

4. If adopted, the key financial implications for the Council are the cost to the HRA of the non-grant funded element of the build costs, and the future revenue costs and income to the HRA of the completed homes.

5. An additional point to note is authority to approve the detailed delivery of schemes within the approved HRA Business Plan was delegated to Affordable Housing Committee by Cabinet on 30 July 2013.

3. Reason for Decision and Options Considered

3.1On 10 February 2015 Cabinet approved the HRA investment and house building programme as part of the Council’s updated 30 year HRA Business Plan. Phase 1 of the HRA capital investment and house building programme is intended to deliver a total of 531 new affordable housing units in years 1 to 5 (2013 – 2018).

3.2As of December 2014, 410 of these new affordable units of Phase 1 were either completed, on-site or in the planning phase of development. All Phase 1 units must be completed by March 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mayor's Housing CovenantReport 103 KB DownloadRead as text

At this meeting

Whole meeting

More from Hounslow Affordable Housing Committee

All decisions
MeetingDecisionOutcome
8 Mar 2023 MO Guidance on Declaring Interests - May 2022There were no declarations of interest. Decided Open
1 Mar 2023 GLA Buyback Programme UpdateThat the Affordable Housing Committee: 1. Approved a £3,200,000 increase in the budget allocation for the care leaver... Approved Open
1 Mar 2023 Chiswick Health Centre UpdateThat the Affordable Housing Committee: Noted the progress of this development since the Affordable Housing Committee ... Noted Open
22 Nov 2021 CEX597 Housing Development Programme for Care Leavers Phase 1That the Affordable Housing Committee: Approved the development of the following HRA sites for residential accommodat... Approved Open
16 Sep 2021 CEX 574: Acquisition of Additional Properties at High Street Quarter, HounslowThat the Affordable Housing Committee: Approved the purchase of 10 additional private market units at High Street Qua... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies