· Members noted the informal consultation to be undertaken on the proposed expansion of the Twickenham Stadium Controlled Parking Zone (CPZ); · Members agreed that the formal (statutory) consultation should be undertaken for those roads in favour of inclusion in the CPZ; · Members agreed that any objections received that remained unresolved are referred to the Chair of this and the Central Hounslow Area Forum, and the respective ward councillors in consultation with the lead officer for resolution; · Members authorised officers to implement the CPZ expansion in the area of support, subject to the provision of a further report detailing any legal and finance implications6being provided to the Chair of this and the Central Hounslow Area Forum for consideration. Councillor Sampson joined the meeting at this point.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
That Members:- (a) Note the informal consultation to be undertaken on the proposed expansion of the Twickenham Stadium Controlled Parking Zone (CPZ); (b) Agree that the formal (statutory) consultation be undertaken for those roads in favour of inclusion in the CPZ; (c) Agree that any objections received that remain unresolved are referred to the Chair of this and the Central Hounslow Area Forum, and the respective ward councillors for resolution; (d) Authorise officers to implement the CPZ expansion in the area of support, subject to the provision of a further report detailing any legal and finance implications being provided to the chair of this and the Central Hounslow Area Forum for consideration.
2. Details
2.1Members will be aware that Twickenham Stadium will co-host a number of international rugby matches during the Rugby World Cup later this year. The competition is scheduled to commence on Friday 18 September 2015. A total of 10 matches will take place at the stadium, including the final on 31 October 2015. Each match is likely to attract capacity spectator numbers of up to 82,000.
2.2The Rugby Football Union (RFU) will be encouraging spectators to travel to the stadium by public transport. It is very likely however that large numbers will also choose to travel by car and seek to park outside the existing Twickenham Stadium CPZ (the ‘R Zone’ CPZ). Recent international matches and music concerts have shown this occurs on a regular basis and there have been calls from residents on the periphery of the CPZ for its expansion.
2.3The extent of parking stress resulting from major events at the stadium was investigated through parking surveys carried out in the periphery of the existing CPZ during the England vs. South Africa international on Saturday 15 November 2014. The survey results were compared with parking activity on a non-match day, with a survey carried out in the same area on Saturday 13 December 2015.
2.4The results show that event related parking does indeed take place beyond the existing R Zone (in L.B. Hounslow roads). To help minimise the impact on residents during the World Cup (and major events thereafter), the RFU has agreed to fund the consultation and expansion of the existing R Zone.
2.5Based on the outcome of the parking surveys, an area had been identified for consultation as shown on the attached map. It encompasses the area bounded by Whitton Dene, Whitton Road, Worton Road and Richmond Road (Ruskin Road, to the north of Worton Road, will also be included).
2.6The consultation will be carried out by consultants appointed by the RFU and implementation where support is identified will be carried out by Hounslow Highways. The consultation is scheduled to take place in March 2015, but the key milestone to achieve is for the expanded scheme to be operational sufficiently in advance of the opening event on 18 September 2015 so that the expanded CPZ can be ‘tested’. The scheme therefore ideally needs to be operational by 1 September 2015.
2.7In light of the ‘purdah’ period coming into effect at the end of March and no meetings of IBAF until June at the very earliest, it is imperative that the formal (statutory) consultation for the R Zone expansion (if supported) is undertaken by June/July 2015 at the very latest to ensure the scheme is operational by 1 September 2015.
2.8Officers therefore request that this Forum delegates authority to the Chair of this Forum and Ward Councillors to consider the outcome of both the preliminary and formal consultations, and to instruct officers accordingly. Also, that an objections received in response to the formal consultation are decided on under similar delegation.
BRIEFING NOTE ENDS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.