That the Cabinet Member for Education and Children’s Services agreed the recommendations of the report as follows: 1. The Cabinet Member noted the progress of the proposals to expand Oaklands School. 2. The Cabinet Member delegated authority to the Executive Director Regeneration Economic Development and Environment (‘Director’) or such officers as may be authorised to act on his behalf to take all necessary actions to progress the procurement and letting of the contracts in consultation with the Lead Member for Education and Children’s Services; to accept and award the construction phase works and other associated costs, professional fees and surveys, subject to the project remaining within budget forecast costs.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
3.1CA449 reported to Cabinet on the outcome of the formal consultation to expand Oaklands School. On 17 March 2015 Cabinet approved the expansion of Oaklands School, subject to planning consent being obtained.
3.2The Local Authority has a statutory duty to provide education for SEN children through the specialist support and teaching that they require to fulfil their potential and be kept safe.
3.3The first element of the proposal to expand Oaklands School is to construct a new-build secondary SEN School for up to 224 children and young adults aged 11-25 on recreational land at Gresham Road, Hounslow.
3.4The second element of the proposal to expand Oaklands School is to convert the existing secondary school in Woodlands Road, Isleworth, to a primary SEN school for up to 90 children.
3.5The Council has limited access rights to the Gresham Road site over land owned by the Hounslow Conservative Club. Discussions to enlarge these access rights as necessary for the new school are ongoing and expected to reach a conclusion before the planning application is decided by the LPA.
3.6The planning application was submitted to the LPA on 10th December 2015 together with a S106A application seeking discharge of an existing planning obligation that currently restricts the site to recreational use.
3.7A contract notice was published in the Official Journal of the European Union (OJEU) and the associated Pre-Qualification Questionnaire process produced a shortlist of six contractors to be invited to participate in a competitive tender process. Invitations to tender were issued to the six firms on 18th January and tender returns are due on 25th March 2016.
3.8A master programme has been developed and the aim is to complete the construction of the new school at Gresham Road in time for the academic year commencing September 2018. The converted school at Woodlands Road is also to be ready to receive Reception children in September 2018. There is little scope for slippage of individual activities without impacting on the overall delivery date.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.