Resolved
Approved, subject to the satisfactory completion of a S.106 agreement.
Planning Committee approved this item on Thursday 10 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Approved, subject to the satisfactory completion of a S.106 agreement.
PLANNING COMMITTEE 10th March 2016 [email protected]
References: P/2014/38367 00461/A/P1
Site: Fountains Close, Feltham.
Description: The construction 99 residential units consisting of 2 x three storey, 3 x four storey and 1 x five storey blocks of flats and 20 houses, with associated access, car parking landscaping, open space and other infrastructure works (the existing 48 flats would be demolished).
This application is being referred back to Planning Committee as a Major Scheme with amended plans and subject to a Section 106 Agreement.
1.0SUMMARY & BACKGROUND
1.1This application was originally presented to Planning Committee in December 2014. At that meeting, the recommendation (to grant planning permission subject to safeguarding conditions and a Section 106 legal agreement to secure the obligations set out in that report) was followed.
1.2As a result of on-going negotiations in respect of the Section 106 legal agreement and to changes to Government legislation, it was necessary to make amendments to the Heads of Terms (see para 8.5 of the December 2014 Committee Report). Further changes were also required to accord with these negotiations and changes in legislation. Consequently a further report was presented to Planning Committee in October 2015 to agree the proposed changes at that time. The Planning Committee followed the Officer’s recommendation to grant planning permission with the amendments as set out in the report and addendum.
1.3Since that most recent resolution, the applicant has requested a number of amendments to the plans previously presented to Committee (details of which are set out below). These amendments could not have been dealt with by way of non-material amendments to the scheme. Given that the Section 106 had still not been signed and the planning permission granted, it was decided that rather than submit a new application (after the issuing of the planning permission), a more appropriate solution was to make amendments to the on- going planning application and refer the application back to Planning Committee for consideration.
1.4The sections of this report which are set out below refer only to the changes and updates necessary to the original Committee Report. Members are requested to refer to the original Committee Report in December 2014 (together with the associated addendum and minute - http://democraticservices.hounslow.gov.uk/ieListDocuments.aspx?CId=595&MI d=8498&Ver=4 ) and the Committee Report of October 2015 (http://democraticservices.hounslow.gov.uk/ieListDocuments.aspx?CId=595&M Id=8846&Ver=4 ).
1.5These reports set out the full details of the application, the material planning considerations and the overall the planning assessment.
1.6No further formal consultation was carried out since the previous resolution but bespoke letter was sent to those who had previously made representations on the application and those whose properties back onto the site (and who would be most affected by the amendments) advising of the amended plans, what the main changes are and that the application would be referred back to Committee on 10th March.
1.7For the reasons set out in the previous reports and below, the scheme is considered to acceptable within its surroundings, providing 99 units of affordable housing on-site (following demolition of existing 48) in a high-quality scheme that provides good standards of accommodation and appropriate access and car parking on site without having an undue impact on adjoining land uses
1.8The application is recommended for approval subject to conditions and a section 106 agreement (Heads of Terms set out below).
2.0POLICY
Determining applications for full or outline planning permission
2.1The determination must be made in accordance with the development plan unless material considerations indicate otherwise. Local finance considerations must also be assessed.
The National Planning Policy Framework
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fountains Close, HanworthReport | 76 KB | DownloadRead as text |
Follow Planning Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Aug 2026 | 80 - 82 Staines RoadResolved – that planning application P/2023/2705, erection of two apartment blocks of 3-5 storeys and 4-6 storeys to ... | Approved | Open |
| 11 Jun 2026 | 64E Waldeck Road, ChiswickResolved – that planning application P/2026/0264, erection of a single storey rear extension to the house, was approv... | Approved | Open |
| 5 Mar 2026 | Central Park EstateResolved – that planning application P/2024/4226, erection of four commercial units of mixed uses B2 (General Industr... | Approved | Open |
| 5 Feb 2026 | Block B, Brentford Lock WestResolved – that planning application P/2025/1313, erection of part 10, part 11 storey building comprising 124 residen... | Refused | Open |
| 5 Feb 2026 | 97 Devonshire RoadResolved – that planning application P/2025/0646 , erection of a rear roof extension with four front roof lights and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.