Temporary closure and access restrictions at Space Waye civic amenity site
AgreedExecutive1 paper
Cabinet Member Single Member Decision agreed this item on Wednesday 10 August 2016. Below is the council's own wording, with the papers it was decided on.
That the Deputy Leader of the Council and Cabinet Member for Environment agreed to the recommendations in the submitted report as follows on grounds of urgency: 1.1 The Cabinet Member agreed the temporary closure of the civic amenity site at Space Waye to allow the site to be reconfigured to receive recycled materials from 31 October 2016 1.2 The Cabinet Member agreed that once re-opened, public access to the site would be at weekends only. 1.3 The Cabinet Member agreed that the above change should apply until the completion of the new depot and Materials Handling Facility at Southall Lane Waste Depot. 1.4 The Cabinet Member agreed to investigate options for the permanent re-development of Space Waye and to report back to Members. 1.5 The Cabinet Member agreed the capital investment of £200k to spend on construction works at Space Waye . This is to be funded from expected £480k revenue savings, which will result from implementation of this proposal.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Cabinet Member Single Member Decision, 7 pages
Report for: ACTION
Contains Confidential No or Exempt Information
Title Temporary closure and access restrictions at Space Waye civic amenity site
Member Deciding Cllr Amrit Mann, Deputy Leader of the Council Contact Details Andrew Baker, Interim Head of Commissioning – Waste and Recycling, Highways PFI and Parking Services 020 8583 2976 [email protected]
Robert Meldrum, Head of Finance, REDe 0208 583 2312 Date to be Considered 10 August 2016 Implementation Date if 22 August 2016 Not Called In Affected Wards All Keywords/Index Waste, Recycle, civic amenity site
SINGLE MEMBER DECISION
1. Details of Recommendations
To agree: - 1.1 Agree the temporary closure of the civic amenity site at Space Waye to allow the site to be reconfigured to receive recycled materials from 31 October 2016 1.2 Once re-opened, to provide public access to the site at weekends only. 1.3 The above change to apply until the completion of the new depot and Materials Handling Facility at Southall Lane Waste Depot. 1.4 Investigate options for the permanent re-development of Space Waye and report back to Members 1.5 Agree the capital investment of £200k to spend on construction works at Space Waye. This is to be funded from expected £480k revenue savings which will result from implementation of this proposal.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why Dates by which they can expect to they will benefit, link to Values notice a difference Innovating – learning from experience Delivery of a new depot at Southall Recycle 360 will take over the Lane and associated materials service delivery from 31 October. handling facility The new depot allows both the waste and the recycling services to operate from a common depot – improving resilience. The materials handling facility allows the council to sell the high quality materials which will be collected at a higher value than co-mingled materials. Spending wisely – every penny counts This proposal represents the best 31 October 2016 value option for the council to mitigate the delayed delivery of the new depot at Southall Lane
2. Report Summary
This report recommends: - 1. The temporary closure of the civic amenity site at Space Waye to allow the site to be reconfigured to receive recycled materials from 31 October 2016 2. Once re-opened, to provide public access to the site at weekends only. The above change to apply until the completion of the new depot and Materials Handling Facility at Southall Lane Waste Depot. 3. Investigate options for the permanent re-development of Space Waye and report back to Members 4. Agree the capital investment of £200k to spend on construction works at Space Waye. This is to be funded from expected £480k revenue savings which will result from implementation of this proposal. 5. Note a contribution toward previously approved revenue savings will be realised as a result of this report being approved as laid out in paragraph 5a.
3. Reason for Decision and Options Considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.