Members resolved to: 1. Delegate authority to the Executive Director for Regeneration, Economic Development & Environment (REDe) to undertake detailed design for the proposals set out in Appendix A of the report (attached to item 8 of the Agenda pack); 2. Delegate authority to the Executive Director for REDe to carry out the required statutory consultation on the proposals; 3. Delegate authority to the Executive Director for REDe to resolve, where possible, any objections received to the statutory consultation; 4. In the event that any objections received remain unresolved, delegate authority to the Chair of the Area Forum to determine the objections, in consultation with the Ward Councillors; 5. If no objections are received, or once any objections received are resolved, delegate authority to the Executive Director for REDe to implement the scheme.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title Hayes Road Congestion Reduction Scheme Officer Reporting Christopher Deakins - Team Leader Contact Details Traffic & Transport Tel: 020 8583 4866 Email: [email protected] For Consideration By Heston and Cranford Area Forum (“the Area Forum”) Date to be Considered 15 September 2016 Implementation Date if 30 September 2016 Not Called In Affected Wards Heston West Ward Keywords/Index Road Widening, Congestion
1. Details of Recommendations
That Members: 1.1 Delegate authority to the Executive Director for Regeneration, Economic Development & Environment (REDe) to undertake detailed design for the proposals set out in Appendix A. 1.2 Delegate authority to the Executive Director for REDe to carry out the required statutory consultation on the proposals. 1.3 Delegate authority to the Executive Director for REDe to resolve where possible any objections received to the statutory consultation. 1.4 In the event that any objections received remain unresolved, delegate authority to the chair of the Area Forum to determine the objections in consultation with the Ward Councillors. 1.5 If no objections are received or once any objections received are resolved, delegate authority to the Executive Director for REDe to implement the scheme.
If the recommendations are adopted, how will residents benefit? The proposal would facilitate the delivery of the If the highway works proposed Hayes Road Congestion Relief Scheme, proceed, it is intended these which will widen Hayes Road to facilitate an would commence during additional westbound traffic lane and remove a 2018 and be completed in highway pinch-point. 2019. The proposal would assist in the economic viability of the area by reducing journey times for freight, bus passengers and general traffic. It would also improve road safety in the wider area by encouraging greater use of the main road and reducing levels of ‘rat- running’ on residential streets. Overall the highway works will make a positive contribution to the economic, social and environmental well-being of the area.
Spending Wisely – Subject to approval, this scheme 2018/19 will be delivered in partnership with Hounslow Highways. This provides time and cost efficiencies in commissioning and delivering the scheme.
Listening / Responding – Liaise with residents during 2017 the statutory consultation.
2. Report Summary
2.1This report details the proposed widening of a section of Hayes Road between Christopher Road and Trade City commercial units. 2.2 It recommends progressing with the detailed design, statutory consultation and construction of the road widening detailed in the report and shown in Appendix A. 2.3 If adopted, the scheme will be wholly funded by Transport for London (TfL) from the approved Local Implementation Plan (LIP) funding. The cost estimate, based on the initial design work undertaken, is £390k (including CPO costs). The scheme is subject to detailed design to determine the final cost estimate and a pricing exercise by Hounslow Highways.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.