That the Affordable Housing Committee: · Noted the update toward the delivery of the Affordable Housing Pledge and, in particular, considered the issues which are likely to affect its future delivery. · Did not reach agreement to amend the definition of affordable housing for the purpose of the Pledge to bring it into line with that of Central Government and the London Plan to include Starter Homes. It was instead agreed to continue monitoring the matter and to bring further information back to the next meeting of the Committee.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Title Delivering the affordable homes target 2014-2018 New and Renewed Risks Officer Reporting Peter Matthew Director Housing Contact Details [email protected] Civic Centre 0208 583 5321 For Consideration By Affordable Housing Committee Date to be Considered 29 September 2016 Implementation Date if Not Called In Affected Wards All Keywords/Index Pledge - Affordable homes target 2014-2018 New and Renewed Risks
1. Details of Recommendations
The report recommend that the Affordable Housing Committee:
Notes the update toward the delivery of the Affordable Housing Pledge and, in particular, considers the issues which are likely to affect its future delivery. Agrees to amend the definition of affordable housing for the purpose of the Pledge is brought into line with that of Central Government and the London Plan to include Starter Homes.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference 2. Report Summary
Pledge Delivery Update
1. The Council has pledge to secure a further 3,000 affordable homes in Hounslow, 400 of which should be new Council houses by 2018. This report updates progress towards this target and the issues affecting its future delivery.
2. As of 31 July 2016, a total of 2,068 affordable homes have been secured representing 69% of 3,000 of the overall target. Of these 1,562 units have been secured through negotiations on planning applications and other sources, and 506 will be delivered through the Council’s new house building programme. This paper considers issues that might affect the delivery of the remaining 932 affordable homes yet to be secured.
3. Reason for Decision and Options Considered
3.1Negotiated Supply 3.1.1 Our ability to fully secure the remaining 1,038 number of units required to meet the target will affected by the following current and emerging factors:
a) Definition of Affordable Housing: for the purposes of the Pledge the Council has adopted the broad definition promoted by Central Government, which includes Discount Market Sale. With the introduction of the Housing and Planning Act 2016 Central Government has further revised this definition to include the new “Starter Homes”. Starter Homes are intended to account for 20% of any major housing scheme before its viability for providing additional affordable homes is tested. The expected effect of this is a significant reduction in the number of negotiated affordable homes secured through S106’s as developers seek to equate their starter homes elements as their affordable housing obligations. In the light of these changes, therefore, we recommend that Committee: Agrees to amend the definition of affordable housing for the purpose of the Pledge is brought into line with that of Central Government and the London Plan to include Starter Homes. Recognises the significant risk to the realisation of the Pledge target as a result of expected reductions in the achievable numbers of “regular” affordable housing tenures.
b) Scheme viability: the development viability of housing schemes will continue to be a big challenge to the delivery of affordable housing through the planning process. The requirement for Starter Homes under the Housing & Planning Bill as mentioned above will have a major impact and is likely to fuel developers’ opposition to providing additional affordable housing on the grounds of scheme viability.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.