Temporary Extension of Loan Facility to Lampton Investment 360 Ltd
AgreedExecutive1 paper
Cabinet Member Single Member Decision agreed this item on Thursday 1 December 2016. Below is the council's own wording, with the papers it was decided on.
That the Cabinet Member agreed a temporary loan to Lampton Investment 360 Ltd up to £285k to enable the purchase of 115 Hatchett Road, Feltham at Bank of England base rate plus 4.5% payable quarterly and to be repaid once a long term financing arrangement is put in place for Lampton Investment 360.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Cabinet Member Single Member Decision, 4 pages
Report for: ACTION/INFORMATION
Contains Confidential or Exempt Information
Title Temporary Extension of Loan Facility to Lampton Investment 360 Ltd Member Deciding Councillor Theo Dennison Contact Details Clive Palfreyman – Director of Finance and Corporate Services Email: [email protected] Tel: 0208 583 6682 Date to be Considered Friday, 23 September 2016 Implementation Date if Friday, 30 September 2016 Not Called In Affected Wards All Keywords/Index Lampton Investment 360 Ltd
SINGLE MEMBER DECISION
1. Details of Recommendations
To agree a temporary loan to Lampton Investment 360 Ltd up to £285k to enable the purchase of 115 Hatchett Road, Feltham at Bank of England base rate plus 4.5% payable quarterly and to be repaid once a long term financing arrangement is put in place for Lampton Investment 360.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference The loan helps facilitate the acquisition of a portfolio March 2017 of properties by Lampton Investment 360 Ltd which will help ease the housing issues currently faced by the borough.
2. Report Summary
1. This report deals with providing an interim loan facility to Lampton Investment 360 Ltd to facilitate the purchase of 115 Hatchet Road Feltham. 2. It recommends the loan is made on the same terms as the loan currently in place with Lampton 360 Ltd with the addition that it be repaid on the establishment of the longer term arrangement between the Council and Lampton Investment 360 Ltd 3. These recommendations are being made because at present work is underway to establish a long term loan arrangement between London Borough of Hounslow and Lampton Investment 360 Ltd so it can purchase properties for residential letting. 4. If adopted, the key financial implications for the Council are an increase in the level of funding provided to the Lampton 360 group of companies.
3. Reason for Decision and Options Considered
3.1Cabinet on 19 July 2016 approved the business plan for Property 360 and the creation of a subsidiary, Lampton Investment 360 Ltd.
3.2Approval was given to agree terms for funding for both development and investment activity, by way of an on-lending facility from LBH to Lampton Development 360 LLP and Lampton Investment 360 Ltd. This work is currently underway and with legal advisors being appointed to draw up loan agreements for the council and Lampton seeking support to review and agree terms.
3.3A property which meets the criteria included in the business plan has been identified, inspected and an offer accepted by the vendor. The full details of the property and the appraisal demonstrating the total cost including all fees and taxes related to the purchase and the cost of some refurbishment and white goods are in line with the requirements of the business plan for Property 360.
3.4The current loan to Lampton 360 Ltd has been offered at Bank of England Base Rate plus 4.5% to be paid quarterly. It is proposed that these terms will apply to the money lent to Lampton Investment 360 Ltd until alternative terms for a loan are agreed or the money is repaid.
3.5By making funds available to Lampton Investment 360 Ltd will be able purchase a property which will be made available for rent as outlined in the business plan.
Option Comments Lend money on the same Allows Lampton Investment 360 Ltd to begin terms as the current loan to Lampton implementing the business plan prior to a 360 Ltd. specific loan agreement being put in place Wait for loan agreement to be Could lead to a delay of up to 2 months put in place before Lampton Investment 360 Ltd is able to start practical implementation of the agreed business plan
4. Key Implications 4.1 Targets and measures to be explained here using either paragraphs or table below or both.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.