That in respect of the release of Capital projects – Medium Term Financial Strategy (MTFS) Capital and reallocation of reserves, the Cabinet Member agreed: 1. That approval is given to the release of £0.7m from the previously allocated £2.9m for the phased playground replacement programme as in the 2011 MTFS. 2. That approval is given to the reallocation of £313,386 already allocated within a Capital reserve for parks improvement. Re-allocating is requested as the original purpose of the reserve is either now met or no longer viable.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
1.0That approval is given to the release of £0.7m from the previously allocated £2.9m for the phased playground replacement programme as agreed in the 2011 MTFS1.
1.1That approval is given to the reallocation of £313,386 already allocated within a Capital reserve for parks improvement. Re-allocation is requested as the original purpose of the reserve is either now met or no longer viable.
1 Cabinet Report CEX051 ‘Capital Programme Review’ 10 February 2015 http://democraticservices.hounslow.gov.uk/ieListDocuments.aspx?CId=571&MId=83 77 If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Customer values: Innovating; improving parks June 2017– March 2018 informed by resident feedback and consultation. A cleaner, greener borough; this work will make June 2017- March 2018 the borough a place where people feel proud to work and live Active, healthy communities; promoting lifestyles June 2017- March 2018 that improve people’s health and wellbeing Brighter futures for our children; giving children June 2017- March 2018 the best start in life
Background
1. The Borough Council authorised a £2.9m playground refurbishment scheme as part of the mid-term financial strategy in July 2011. Refurbishment to 21 sites has been completed at a cost of £2.2m; leaving £700k uncommitted after a freeze in capital expenditure was introduced in 2014. In addition to the £700k there is also an additional £313k of capital reserves available which has been earmarked for parks improvement.
2. The remaining funding is not sufficient to complete all the playground capital works that are now required. The leisure team have reviewed the remaining playground sites which need refurbishment to ensure that remaining money is spent on sites where it is most needed in terms of: health and safety requirements targeting investment to areas of greatest need; in terms of areas where children’s access to outdoor space may be limited
3. This review has helped to identify the key sites for investment of the available unallocated reserves. Additional funding will have to be sought from capital reserves or S106 to fund any further future works as when they are required.
4. The priority sites that have been identified for major improvements include; Redlees Park Playground (Isleworth Ward), Carville Hall North Playground (Brentford), Hawthorn Hatch Playground (Syon) & St Dunstan’s Park Playground (Feltham West). An estimated cost of £170 – 250k per site.
5. The following priority sites have been identified for partial improvement works for health and safety reasons; Southville Park Playground (Cage Park, Bedfont) and South Road Rec Playground (Hanworth). The estimated cost per site is £40-60k.
6. These recommendations are being made because the council has a responsibility to ensure our parks and open spaces meet health and safety standards and are supportive of health and wellbeing for children and families. The outcome will be improved, safe play spaces that encourage activity and help us to tackle the rising levels of obesity in our children and young people. 3. Reason for Decision and Options Considered
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.