2017/18 DSG Budget Update

Noted Committee 1 paper

Schools Forum noted this item on Monday 26 February 2018. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That the 2017/18 forecasted DSG outturn position be noted.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Schools Forum

Recommendation

That Schools Forum note the 2017/18 forecasted DSG outturn position.

2. Report Summary

This report updates Schools Forum on the forecasted 2017/18 DSG outturn position. As at 31 January 2018 there is a projected overspend of £0.21m against the 2017/18 DSG budgets. This represents a projected overspend of £0.37m against the high needs block which is offset by a projected underspend of £0.16m against the early years block. This compares to a projected shortfall of £0.9m when the 2017/18 budget was set.

3. 2017/18 forecasted outturn position

3.1The table below shows the current forecasted position against the updated DSG allocations for 2017/18.

Forecast @ 31 January 2018

Schools Early Years High Needs Total £m £m £m £m Expenditure: Budgeted * 101.15 18.17 44.29 163.61 Forecasted 101.20 17.52 44.28 163.00 (under)/over 0.05 (0.65) (0.01) (0.61)

Income: Budgeted * 101.15 18.17 44.29 163.61 Forecasted 101.20 17.68 43.91 162.79 (under)/over (0.05) 0.49 0.38 0.82

Net Variance 0 (0.16) 0.37 0.21 *net of recoupment

3.2The budgets in the table above include the approved transfer of monies from the schools’ block to the high needs block. The forecasted income also reflects any updates made to the 2017/18 DSG allocations since the budget was set.

3.3When the original budget was set, it was anticipated that there could be a shortfall of £0.9m in the 2017/18 budget requirement against the available DSG allocation which would be funded from DSG reserves; £0.47m in early years and £0.39m in high needs.

3.4The outturn position for 2017/18 is currently forecasted to be a net under spend on the early years budget of £0.16m and a net overspend of £0.37m in high needs, giving an overall net overspend of £0.21m across the two blocks.

4. Early Years Block

4.1The net position forecasted for early years is an underspend of £0.16m which is made up of:

• £0.21m overspend - 2 year old provision • £0.80m underspend - 3 year old provision • £0.49m overspend – due to a provision for clawback on funding • £0.07m underspend – other areas.

4.2An overspend is projected against the 2 year old provision. This reflects the reduced level of government funding in 2017/18. The level of take up is also lower than was expected. We have therefore had to make provision for an anticipated clawback of funding (which will be through an adjustment to the Early Years Block in 2018/19).

4.3An underspend is projected against the 3 & 4 year old provision. Whilst there has been an increase in the number of applications for the extended 30 hours provision, there has been a decrease in the number of places accessed in schools and PVI sectors for the core 15 hour entitlement. This has reduced the level of expenditure on 3 & 4 year old provision.

4.4As the number of places are lower than anticipated and less than the places for which we have received funding we have made provision for amounts to be repayable back to the DfE for both the core 15 hours and extended 15 hours funding (which will be through an adjustment to the Early Years Block in 2018/19). 4.5 The reduction of DSG income received in year of £0.49m reflects the provision for clawback of funding estimated at £0.3m for 3 & 4 year olds and £0.2m for 2 year olds due to lower numbers of 2 year old and 3 & 4 year olds.

5. High Needs Block

5.1The net outturn position for the high needs provision is forecasted to be a £0.37m over spend. The projected overspend is made up as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2017/18 DSG Budget UpdateReport 183 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Hounslow

Search all
  1. 2017/18 DSG Budget UpdateThis decision
  2. 2026/27 DSG Schools Block BudgetAgreed
  3. 2024-25 DSG Schools Block BudgetAgreed
  4. 2023024 CSSB DSG Block BudgetAgreed
  5. 2020/21 DSG Budget OutturnNoted
  6. DSG High Needs budget deficit plan update (Annita Cornish)Noted

More from Hounslow Schools Forum

All decisions
MeetingDecisionOutcome
23 Feb 2026 Finance UpdateTo note the finance update Noted Open
23 Feb 2026 Early Years Budget and Hourly Rates 2026/27Resolved : Schools Forum noted: 1. Feedback from the consultation with early years providers on the 2026/27 early yea... Noted Open
23 Feb 2026 High Needs Budget 2026/27Schools Forum noted 1. noted the provisional 2026/27 High Needs (HN) budget requirement of £83.37M as proposed by the... Noted Open
23 Feb 2026 SEND & Alternative Provision Improvement Programme UpdateResolved : To note the update Noted Open
23 Feb 2026 Forward PlanResolved : 1. Schools Forum agreed the change in format for future Schools Forum meetings. Action: Members requested ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies