Resolved

That Councillor Amrit Mann, Cabinet Member for Environment, decided to rescind the Single Member Decision taken in September 2017 and approved the extension of the current parking contract to Sunday 16 December 2019.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Cabinet Member Single Member Decision

Report for: ACTION/INFORMATION

Contains Confidential No or Exempt Information

Title Extension of Parking Contract to December 2019

Member Deciding Cllr Amrit Mann, Cabinet Member for Environment

Contact Details Victoria Lawson, Director of Customer Services and Communications

Date to be Considered 23 April 2018

Implementation Date if 3 May 2018 Not Called In Affected Wards All wards

Keywords/Index Parking, contract

SINGLE MEMBER DECISION

1. Details of Recommendations

To rescind the Single Member decision taken in September 2017 and approve the extension of the current parking contract to Sunday 16 December 2019.

If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference

2. Report Summary

In March 2013, Cabinet agreed to award a joint contract for parking services to Serco Limited for an initial contract period of five years with the option to extend for a further period of five years.

The initial five-year period of the contract ceases in July 2018. This report recommends the extension of the contract to Sunday 16 December 2019 to allow suitable time to recommission a new parking service for the council.

The financial impact of this contract extension will be a budget pressure equivalent to £0.6m, it is proposed to fund this through the inflation budget for the period of the extension.

This decision would replace the Single Member Decision taken in September 2017.

3. Reason for Decision and Options Considered

3.1In March 2013, Cabinet agreed the award of the joint contract for parking services to Serco Limited for an initial contract period of five years with the option to extend for a further period of five years. The initial five year period of this contract ceases in July 2018.

3.2There are several drivers for extending the contract to allow time to reconsider and potential reshape the parking offer to residents:

 With changing demands in Hounslow, we need to develop a new parking offer for our residents that balances the reduction in car parks to build much needed housing for residents; whilst managing within a revised and reducing financial envelope.

 We need to develop a new parking strategy and policy framework in line with a reduced financial envelope and consider any advances within the field.

 We need to determine the most appropriate model for future delivery and the options for taking this forward for consideration by Cabinet.

 We need to engage with a specialist parking consultant with a specific brief to outline what a parking offer looks like within the financial envelope and to support the development of a revised strategy and policy framework.

3.3A Single Member Decision had been taken in September 2017 to seek an extension of no more than one year to July 2019. In that report, it was stated that: the Council does not have an absolute contractual right to extend for a one year period. Such an extension, and the price, will be a matter for negotiation with Serco.

3.4These negotiations have now concluded and a contract extension to December 2019 is more feasible. This report therefore seeks to amend the original decision to seek approval for the extension to be until Sunday 16 December 2019. Subject to the approval of the Single Member Decision, formal notification will be provided to SERCO. 3.5 The recommendation is, therefore, to extend the contract to Sunday 16 December 2019 to allow suitable time to recommission a new parking service.

4. Key Implications

4.1By allowing appropriate time to consider both the future parking strategy, policy framework and therefore future parking offer for residents we will be able to recommission a new service based on agreed outcomes with Members and residents.

5. Financial Details

a) Financial Impact On The Budget (Mandatory)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extension of Parking Contract to December 2019Report 273 KB DownloadRead as text
PDF
General UrgencydocReport 192 KB Download

At this meeting

Whole meeting
1Extension of Parking Contract to December 2019This decision

On this subject at Hounslow

Search all
  1. Extension of Parking Contract to December 2019This decision
  2. Extension to Parking ContractApproved
  3. Teesdale Avenue and Teesdale Gardens -Extension of the West Middlesex Hospital Controlled Parking Zone (CPZ) - Mark Frost (LBH)Agreed
  4. 2 Redlees Close, Isleworth: erection of a two storey attached house with associated parking and erection of a single storey rear extension to the existing house.Approved
  5. Hounslow Town Centre Parking Scheme - Proposed ExtensionNoted

More from Hounslow Cabinet Member Single Member Decision

All decisions
MeetingDecisionOutcome
6 Oct 2026 New Residential Children's Home: Approval of Additional Capital Funding and Contract AwardThat Councillor Shantanu Rajawat, Leader of the Council, agreed to: 1. Approve an additional capital budget allocatio... Agreed Open
7 May 2026 Cedars Special School Expansion to Key Stage 3 and Key Stage 4That Councillor Tom Bruce, Deputy Leader of the Council and Portfolio holder for Assets, Regeneration and Development... Approved Open
27 Jan 2026 In-year revisions to fees and charges for the provision of CCTV footage and applications for Section 61 consentThe Leader of the Council approved the following fee and charge revisions: 1. Introduction of a sliding scale of char... Approved Open
13 Jun 2025 Decision on Report from Local Government Ombudsman in relation to a Homeless CaseThat Councillor Shantanu Rajawat, Leader of the Council and Cabinet Member for Strategy, Resources and External Affai... Noted Open
29 Sep 2021 CEX589 - Tender for Children's Cycle Training ProviderThat Counci l lor Hanif Khan, Ca b in e tMe m be r Transport and One Hounslow: 1.1 Agreed that Hounslow begins the te... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies