Resolved
That the report be noted.
HOUNSLOW PRE-APPLICATION PROPOSAL FORUM – PROTOCOL
Purpose
This Protocol provides a framework within which prospective developers may present their emerging development proposals to Members of the Council on a ‘without prejudice’ basis, prior to making a formal application for planning permission to the Council. It sets out how the Pre-Application Proposal Forum (the “Forum”) works.
Guiding Principles
The Council encourages pre-application discussions with developers who are preparing proposals for major and development proposals. The Forum provides an opportunity for developers to present proposed schemes to Members to explain the proposal and consider community feedback prior to making an application. This will enable Members to represent their community and keep them informed about development proposals in their area.
The Forum considers proposals as part of the pre-application process, with most pre- application proposals to be managed through a Planning Performance Agreement (PPA) between a developer and the Council. However the Forum may also provide an opportunity to discuss current planning applications that are of a strategic or complex nature, which would benefit from more detailed review and explanation.
The Forum provides an opportunity for open exploration of the issues in a relatively informal atmosphere and may help to identify problems that could be resolved in advance of the formal submission of an application. Whilst developers are encouraged to use this opportunity, where appropriate, it is not mandatory and the Forum is not a decision making body of the Council.
Although the Forum would be held in public, it would not be a public meeting where members of the public would lobby in support or opposition to the proposal or where the scheme is negotiated in public. Additionally it would not be possible to ensure that all issues are addressed and identified and the Forum is not intended to take the place of structured pre- application discussions and negotiations. It would also not take the role of the Planning Committee, or delegated officer decisions, which have the regulatory function of determining planning applications after submission. The Forum will not be minuted, though notes of observations made by Members may be taken.
This Protocol aims to ensure an open and transparent process by clearly outlining how the Forum will take place ensuring there is a consistent approach and setting out actions and behaviours to be adhered to by all parties. The overall objective is for subsequent planning applications to be based on a better understanding of the key issues, for Members and planning officers to be better informed when taking decisions and to make it easier to determine major planning applications.
Proposals
Complex and major development proposals (more than 10 dwellings or 1,000sqm of floor space) or those with significant environmental effects and subject to a Planning Performance Agreement are considered suitable for the Forum. In some instances current applications that are of a strategic or complex nature may also be considered. Presentation of proposals to the Forum shall be subject to the discretion of the Chair of the Planning Committee in consultation with the Head of Development Management. 1 Forum Schedule and Notice
Pre-Application Proposal Forums shall be scheduled to be one evening a month, 2 weeks after each Planning Committee (or as otherwise arranged by the Head of Development Management with agreement of the Chair of the Planning Committee). Notice of a forthcoming presentation shall be given at the preceding Planning Committee. All Planning Committee Members, Ward Members and registered amenity and community groups affected by the proposal shall be given notice of the Forum presentation by email from the Council’s PPA Planning Officer at least 7 days prior to the Forum date.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Pre-app forum protocolAppendix | 3 pages | DownloadRead as text |
PDF |
Pre-application Forum Agenda ReportAppendix | 1 pages | Download |
Follow Planning Committee at Hounslow and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Aug 2026 | 80 - 82 Staines RoadResolved – that planning application P/2023/2705, erection of two apartment blocks of 3-5 storeys and 4-6 storeys to ... | Approved | Open |
| 11 Jun 2026 | 64E Waldeck Road, ChiswickResolved – that planning application P/2026/0264, erection of a single storey rear extension to the house, was approv... | Approved | Open |
| 5 Mar 2026 | Central Park EstateResolved – that planning application P/2024/4226, erection of four commercial units of mixed uses B2 (General Industr... | Approved | Open |
| 5 Feb 2026 | Block B, Brentford Lock WestResolved – that planning application P/2025/1313, erection of part 10, part 11 storey building comprising 124 residen... | Refused | Open |
| 5 Feb 2026 | 97 Devonshire RoadResolved – that planning application P/2025/0646 , erection of a rear roof extension with four front roof lights and ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.