CEX318: Regeneration and Economic Development Strategy 2016 - 20: Projects Update 2018
NotedExecutive2 papers
Cabinet Member Single Member Decision noted this item on Monday 15 October 2018. Below is the council's own wording, with the papers it was decided on.
That Councillor Steve Curran, Leader of the Council and Cabinet Member for Corporate Strategy, Planning and Regeneration: 1. noted the progress made over the past year on the projects listed in the Regeneration and Economic Development Strategy 2016 – 2020; and 2. noted that a report will be brought to the November 2018 Cabinet Meeting that will propose a new, more strategic approach to prioritisation for investment and delivery of projects in line with the overarching objectives set out in the current Regeneration and Economic Development Strategy 2016 – 20.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Cabinet Member Single Member Decision, 9 pages
Report for: INFORMATION
Contains Confidential No or Exempt Information Title CEX318: Regeneration and Economic Development Strategy 2016 – 20: Projects Update 2018 Member Reporting Councillor Steve Curran, Leader of the Council and Cabinet Member for Corporate Strategy, Planning and Regeneration; [email protected] Contact Details Peter Matthew Strategic Director Housing, Planning and Communities Tel: 020 8583 5321/5340 Email: [email protected]
Joyce Ip Acting Team Leader of Housing Zones & Regeneration Tel: 020 8583 4237 Email: [email protected] Date to be Considered 15 October 2018 Implementation Date if 25 October 2018 Not Called In Affected Wards All Keywords/Index Regeneration, strategy, investment, economic, growth, development, Golden Mile, town centre, infrastructure, Hounslow, Brentford, Feltham, Chiswick, planning, Heathrow, business, West of Borough, Plan.
SINGLE MEMBER DECISION 1. Details of Recommendations
1. To note the progress made over the past year on the projects listed in the Regeneration and Economic Development Strategy 2016 – 2020. 2. To note that a report will be brought to the November 2018 Cabinet Meeting that will propose a new more strategic approach to prioritisation for investment and delivery of projects in line with the overarching objectives set out in the current Regeneration and Economic Development Strategy 2016 – 20. 2.
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference Regeneration proposals can improve the Some of the projects listed in provision of health, leisure, sports, open space, the strategy have secured education and training facilities, quality of funding to proceed further housing, living environment, job opportunities while some, as stated clearly before, during and after development is in the strategy, are yet to complete, improved public transport facilities, secure commitment from our physical security and other crime prevention partners. We expect different measures for existing residents and new arrivals rates of implementation over to the area. the next 2 years and beyond.
2. Report Summary
2.1On 15 March 2016, the Borough Council approved the Regeneration and Economic Development Strategy 2016 - 2020. This strategy sets out the regeneration and economic development principles and interventions for the borough. It outlines the council’s plans to achieve lasting and successful regeneration and economic development and the role the council plays and making that happen.
2.2The strategy contains priorities for actions and projects which will help achieve our regeneration and economic development objectives or unlock and deliver sustainable growth across the borough. Some of the projects are yet to secure funding – a key role of this strategy is to act an investment tool to gain external funding.
2.3The Regeneration and Economic Development Strategy 2016 - 2020 is subject to regular review and update to ensure that the document remains valid during the plan period. The Borough Council on 15 March 2016 also agreed the lists of projects in the strategy would be updated annually to remove and report on projects which have been delivered or are no longer deliverable and to include new projects as they emerge.
2.4This report gives an update on the projects listed in the Regeneration and Economic Development Strategy 2016 – 2020 and the detailed analysis is included at Appendix 1.
3. Reason for Decision and Options Considered
3.1Hounslow Council’s commitment to regeneration and economic development has been embedded throughout its services and is referenced in other adopted strategies and plans. The Regeneration and Economic Development Strategy 2016 – 2020 amalgamates these elements including projects into one single document so that their progress can be monitored.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.