a) That planning permission for planning application 01054/215-223/P18 for the demolition of existing buildings and the erection of a part three, part four storey building (block A) to the front and a five storey building (block B) to the rear of the site providing a total of 47 residential units comprising 15 one bed flats and 32 two bed flats situated around a central courtyard, providing 4 blue badge car parking spaces at ground floor level, communal amenity space at ground floor and roof terraces to both blocks and associated access off Staines Road and landscaping at be approved, subject to the conditions set out in the report and the prior completion of a satisfactory S.106 agreement or unilateral undertaking, set out in section 12.0 of the report and the addendum report and heads of terms as set out in section 9.5 of the report and the addendum report. b) That officers confirm with Leisure Services that the £9k contribution to Midsummer Park is sufficient for required improvements.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Proposal: Demolition of existing buildings and the erection of a part three part four storey building (Block A) to the front and a five storey building (Block B) to the rear of the site providing a total of 47 residential units comprising 15 one bed flats and 32 two bed flats situated around a central courtyard, providing 4 Blue Badge car parking spaces at ground floor level, communal amenity space at ground floor and roof terraces to both blocks, and associated access off Staines Road and landscaping
Drawing See end of report Numbers:
This application is being reported to Planning Committee as it is a Major Development with a S106 agreement attached. 1.0 SUMMARY
1.1This application was deferred by Planning Committee on 1st November 2018 to allow for points to be addressed in relation to the affordable housing offer and the amenity space provision on site.
1.2This is a summary report provided for the purposes of updating the Committee in relation to the reasons for deferral. The main report (Appendix 1) outlines the key details of the application.
Approval of the planning application is therefore recommended subject to the completion of a Section 106 Legal Agreement.
2.0CONSULTATIONS
2.1261 neighbouring residents and businesses were re-consulted on the revised plans on 21/11/2018. A further three responses were received (two in objection and one in support). The objection raised concerns relating to parking and traffic congestion and these have been considered in the main report (Appendix 1).
3.0HOUSING MIX 3.1 The housing mix has been revised from the previous iteration of the proposal presented to committee in November to remove the six studio flats and replace these with four two-bedroom three-person flats. As a result, the overall number of flats has reduced from 49 to 47.
3.2The housing mix would continue to be acceptable in the absence of the studio flats, and the reduction of overall flats on site resulting from this change would be marginal and therefore this amendment is considered to be acceptable.
4.0AFFORDABLE HOUSING
4.1The affordable housing offer has now been revised to provide 40.4% (19no) on-site affordable housing provision. This is an increase from the previous offer of 31% (15no) presented to committee in November.
4.2The mix of the affordable housing offer has been revised from the previous application presented to the committee. The number of London Affordable Rent units remains at eight, and the number of shared ownership units has been increased from seven to 11. The additional units are provided as two-bedroom four-person flats.
4.3In respect of the revised offer, the Financial Viability Assessment highlights that this offer has a negative impact on the development viability, as confirmed by the Council’s Viability Consultant. The Council’s Affordable Housing Team has confirmed that this offer is acceptable and therefore represents the maximum reasonable amount of affordable housing that can be achieved on site.
4.4The offer would therefore be acceptable and would contribute to the Council’s Affordable Housing pledge.
5.0AMENITY SPACE
5.1The scheme has been revised to provide a further 95m2 of amenity space through the provision of a roof terrace atop of Block B.
5.2The prosed amenity space would continue to fall below the required levels but the proposal would now provide 46.5% of the policy requirement compared to 27% in the November scheme. Notwithstanding the proposal remains contrary to Local Plan Policy SC5, and it is extremely unfortunate that an acceptable level of amenity space has not been provided in this scheme.
5.3The use of the roof terrace would be restricted to occupants of flats within Block B, but given that occupants of Block A would have more direct access to other amenity space; this is considered to be acceptable.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.