Meadowbank digital skills suite additional funding
ApprovedExecutive1 paper
Cabinet Member Single Member Decision approved this item on Tuesday 7 July 2020. Below is the council's own wording, with the papers it was decided on.
That Councillor Tom Bruce, Cabinet Member for Education, Youth and Children’s Services, approved: 1. increased budget allocation of £245k to meet the revised estimated cost of the Meadowbank Digital Classrooms and Learning Resource Centre project; and 2. the allocation of additional external Education and Skills Funding Agency funding of £245k to fund the additional cost of this project.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Report to Cabinet Member Single Member Decision, 7 pages
Report for: ACTION
Contains Confidential No or Exempt Information
Title Meadowbank Adult Education Centre Digital skills suite Member Deciding Councillor Tom Bruce, Cabinet Member for Education, Youth and Children’s Services Contact Details Vicki Taylor, Assistant Director (Interim) Education & Skills 020 8583 6093, [email protected]
Date to be Considered 07 July 2020 Implementation Date if 17 July 2020 Not Called In Affected Wards All Keywords/Index Adult, community, education, training rooms.
SINGLE MEMBER DECISION 1. Details of Recommendations
1. To approve an increased budget allocation of £245k to meet the revised estimated cost of the Meadowbank Digital Classrooms and Learning Resource Centre project 2. To approve the allocation of additional external Education and Skills Funding Agency funding of £245k to fund the additional cost of this project
If the recommendations are adopted, how will residents benefit? Benefits to residents and reasons why they will benefit, Dates by which they can link to Values expect to notice a difference The development of new specialist training rooms for Adult community education on the current Meadowbank Adult education centre site.
The intended benefits and outcomes for Hounslow residents are:
Increased opportunities for residents to engage Feb 2021 in digital skills for work training and community education including family learning.
Adult education courses have a number of wider July 2021 benefits. Many learners on our current programmes have reported that they have improved their job prospects, feel less isolated and have improved their health and wellbeing. By increasing the capacity to deliver adult learning, Hounslow residents will further benefit from these programmes.
There will be increased opportunities to engage July 2021 with hard to reach groups and those furthest from learning.
2. Report Summary
This report recommends increasing the Meadowbank digital skills capital budget by £245k with the additional cost being met from from external funds. The project is for the establishment of specialist training facilities to offer new training opportunities for residents of Hounslow in the growing digital skills sector. The Media Tech, ICT and Digital sector in Hounslow is recognised as a growth area, which significantly contributes to the local economy. Local employers’ site key challenges in recruiting to specific jobs locally; key skills required IT development and software skills, coding all of which are found in roles across the ICT and Media sectors.
With the dedicated suite at the Meadowbank Adult Education Centre the service will be supporting the Borough’s post COVID-19 recovery by enabling adults will to retain, upskill and access work experience and be supported into employment in the digital sector.
3. Reason for Decision and Options Considered
This report deals with the development of digital skills classrooms and a Learning Resource Centre (LRC) at the Meadowbank Adult Education Centre to enable the development of a digital skills curriculum offer. This project is 100% externally funded (by Greater London Authority and Education and Skills Funding Agency) so has no impact on council budgets.
In July 2019 this project was approved via single member decision CEX394 with a budget allocation of £950k.Excess external funds of £80k from a previous Meadowbank project (2CP027) were also allocated to this project giving a total budget of £1,030,000
Having completed a tendering process and increase in size of build to accommodate the learning resource centre and additional storage to future proof usage of the building(it is more economical to do this now rather than as a separate project) the cost of the project is higher than the original estimated budget, hence, the recommendation to allocate further available external funds. The expected completion date of the project is now February 2021 rather than the original estimated completion date of Sept 2020
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.