That the Affordable Housing Committee approved, subject to the granting of planning permission for the development: 1. The inclusion of the proposed residential element of the redevelopment of Chiswick Health Centre into the existing 2020 HRA Business Plan, 2. Entering into a Development Agreement and Agreement for Lease with NHS Property Services (NHS PS) for the redevelopment of Chiswick Health Centre which will provide 55 new council homes, at a total scheme cost detailed in confidential Appendix 1; 3. The joint appointment, with the NHS PS, of the design and contract management team to deliver the joint procurement of a suitable contractor; 4. The acquisition of a 250-year lease from NHS Property Services; and 5. The scheme as a Local Lettings scheme, for the benefit of eligible local NHS key workers on the Councils Housing Register, such as nurses and other key health employees. 6. The Affordable Housing Committee also agreed to grant delegated authority to the Executive Director of Housing, Planning and Communities, in consultation with the Lead Member for Corporate Strategy, Planning and Regeneration, to undertake the necessary legal processes to deliver the proposals; to finalise the terms of the lease, the works contracts; the nominations arrangements; to enter into joint appointment with NHS PS for the existing and future consultant appointments, if required, to progress the planning, tendering and construction ... view the full minutes text for item 27.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Contains Confidential No to report and Appendix 2 and 3 or Exempt Information Yes to Appendix 1, – This Appendix contains exempt from publication under paragraph 3 of Schedule 12A of the Local Government Act 1972 (as amended) as it includes information relating to the financial and business affairs of the Council.
Title Proposed Council Housing Development Scheme at Chiswick Health Centre, Chiswick
Member Reporting Councillor Steve Curran – Leader of the Council and Cabinet Member for Corporate Strategy, Planning and Regeneration [email protected] Contact Details Peter Matthew – Executive Director of Housing, Planning and Communities Tel: 0208 583 5321 [email protected] For Consideration By Affordable Housing Committee Date to be Considered 29th March 2021 Implementation Date if 8th April 2021 Not Called In Affected Wards Turnham Green Keywords/Index Council, Build Programme, Social Housing, Affordable Housing, HRA, Council housing, Registered Providers, Pledge.
1. Details of Recommendations
It is recommended that the Affordable Housing Committee, subject to the granting of planning permission for the development, approves: 1. The inclusion of the proposed residential element of the redevelopment of Chiswick Health Centre into the existing 2020 HRA Business Plan, 2. Entering into a Development Agreement and Agreement for Lease with NHS Property Services (NHS PS) for the redevelopment of Chiswick Health Centre which will provide 55 new council homes, at a total scheme cost detailed in confidential Appendix 1, 3. The joint appointment, with the NHS PS, of the design and contract management team to deliver the joint procurement of a suitable contractor, 4. The acquisition of a 250-year lease from NHS Property Services, 5. The scheme as a Local Lettings scheme, for the benefit of eligible local NHS key workers on the Councils Housing Register, such as nurses and other key health employees.
The Report also recommends: 6. That the Committee grants delegated authority to the Executive Director of Housing, Planning and Communities, in consultation with the Lead Member for Corporate Strategy, Planning and Regeneration, to undertake the necessary legal processes to deliver the proposals; to finalise the terms of the lease, the works contracts; the nominations arrangements; to enter into joint appointment with NHS PS for the existing and future consultant appointments, if required, to progress the planning, tendering and construction phases in accordance with the Council’s contract standing orders.
If the recommendations are adopted, how will resident’s benefit? Benefits to residents and reasons why they will Dates by which they can benefit, link to Values expect to notice a difference The proposals seek to build 55 residential homes as 2023 part of a wider redevelopment of Chiswick Health Centre, which will provide modern health facilities for residents in practice area. The proposals seek to build 55 residential homes as 2023 part of a wider redevelopment of Chiswick Health Centre, which will provide affordable homes for key health workers. The construction phase of the development would 2022/23 create temporary construction jobs in the local area and contribute to the Keeping It Local initiative.
2. Report Summary
This report sets out the details of a proposed partnership with the NHS Property Services (NHSPS) to redevelop the Chiswick Health Centre, Fishers Lane, Chiswick, W4 1RX for a new Medical Centre and new Council residential flats. The scheme has been submitted for planning permission which has not yet been determined. Consequently, these proposals are subject to the scheme being approved by the Local Planning Authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.