The direct award of the CCTV Maintenance Contract between the Council and Tyco & Fire Integrated Solutions (UK) Limited t/a Tyco Integrated Fire & Security was approved for twelve months from 1st April 2025 to 31st March 2026 at the value of £537,012.
Word for word from the decision Hounslow published for this meeting.Source: democraticservices.hounslow.gov.uk
Key Decision made by a Chief Officer in accordance with Part 4E Council’s Constitution. (4E_Access_to_Information_Procedure_Rules_agreed_at_Council_26_November_2024_dec24 (4).pdf)
Date of Decision 22nd April 2025
Report Title Direct award of CCTV Maintenance Contract
Name and title of Mandy Skinner Chief Officer Interim Chief Executive
Directorate Communities and Strategy
Name and title of any Councillor Raghwinder Siddhu, Lead Member Public Cabinet member Safety, Regulatory Services and Enforcement consulted
Does the Chief Officer have a conflict of interest No
The Chair of Overview and Scrutiny has agreed that in light of the urgency of putting arrangements in place, this Deadline for call-in decision will not be subject to the call in provisions contained in the Overview and Scrutiny Procedure Rules set out in Part 4c of the Council’s constitution.
Implementation Date Immediately (if not called in)
Affected Wards All
Approved by
Page 1 of 8 1. Recommendations
To approve the direct award of the CCTV Maintenance Contract between the Council and Tyco & Fire Integrated Solutions (UK) Limited t/a Tyco Integrated Fire & Security for twelve months from 1st April 2025 to 31st March 2026 at the value of £537,012.
2. Report Summary
2.1In 2020, the Council entered a four-year CCTV Maintenance Framework Contract with Ealing, Islington and Southwark. The procurement was led by the Council. This contract expired on 31st March 2025.
2.2The contract was for fully comprehensive repairs and maintenance service for CCTV cameras, all technical equipment in the CCTV control and server rooms, remote sites and wireless networks. Also included were goods and services for new CCTV installations.
2.3The maintenance and installation of CCTV plays a fundamental role in ensuring the cameras across the borough are working, because they contribute to the Council’s ambitions on keeping Hounslow safe and managing traffic contraventions.
2.4It has not been practicable to put alternative arrangements in place in time to complete a full procurement exercise prior to the expiry of the current framework contract. The work on the new framework involving all four boroughs has taken longer than expected due to the complex nature of the work required. Also, the lead borough required more time to gain internal approval to carry out procurement for a new framework in 2025. The delay has provided an opportunity for the Council to use the 12-month direct award period to consider all delivery and procurement options.
2.5Schedule 5, paragraph 7 of the Procurement Act 2023, allows the Council to continue to use a supplier to avoid a detriment to the delivery of any of its functions. On the basis that a change in supplier at this stage would result in disproportionate technical difficulties in operation or maintenance, a direct award is recommended.
2.6To ensure the successful continuity of the Council’s CCTV functions, it is recommended a direct award is approved for the CCTV Maintenance Contract between the Council and Tyco & Fire Integrated Solutions (UK) Limited t/a Tyco Integrated Fire & Security for twelve months from 1st April 2025 to 31st March 2026 at the value of £537,012. The terms and conditions will remain the same as those in the contract, which ended on 31st March 2025.
Page 2 of 8 2.7. There is an increase of £97,139 in the contract value compared to last year. This increase is due to 130 new cameras having been added to the network throughout 2024-2025 and the full 12-month’s maintenance costs included in the price for 2025-2026.
2.8The proposed 12-month direct award of the contract will allow the Council to consider all delivery and procurement options from 1st April 2026.
3. Background and links to Corporate Priorities
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.