Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)

Decided Finance 2 papers

AI summaryHounslow's Audit and Governance Committee noted the Q1 2026-27 Corporate Risk Register, covering 15 risks with the highest residual scores on cyber security, children's safeguarding and climate resilience.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedNo resolution to approve or reject; report received
MoneySeveral large sums referenced£51.5m budget gap, £15m prior overspend, £18m school deficit forecast
What happens next2027/28 budget process about to startWorkforce Strategy 2026-2030 to be finalised
Who it affectsCouncil services, residents, tenantsSchools, social housing tenants, vulnerable children and adults

What was decided

The committee received the Q1 2026-27 Corporate Risk Register update from the Director of Strategy, Performance and Commissioning, who answered members' questions. Report P1

The register tracks 15 corporate risks covering regeneration, building safety, social housing regulation, safeguarding, counter-terrorism, cyber security, workforce, climate, financial resilience and schools. Report P1

Why

Officers presented the register so members could scrutinise how key risks to council services and residents are being managed and what controls are in place. Report P1

Several risks show movement: workforce in social care down by 8, terrorist threat up by 3, social housing regulation and cyber up by 1, and safeguarding of children and climate down by 1. Report P6, P7, P8, P9, P10, P11

What happens next

The Council is about to commence the 2027/28 budget process, aiming to clear the structural budget gap. Report P11

The Council is to finalise and implement the Workforce Strategy 2026-2030 and to implement the Climate Change Resilience Plan. Report P10, P11

Hounslow's Building Safety Regulator cases are to be progressed, with further submissions required by December 2026, and Hounslow becomes a collecting authority for the Building Safety Levy from October 2026. Report P3, P4

The money

  • £51.5m Budget gap identified for 2026/27, rising to £91.3m by 2028/29 Report P11, P12
  • £20m Replenishment of reserves committed to by 2027/28 Report P11
  • £15m Overspend in 2024/25 Report P12, P13
  • £2.5m Aggregate school deficit at end of 2025/26, up £5.2m on prior year Report P15
  • £18m Three-year aggregated and unmitigated schools deficit forecast Report P15
  • £1.0m Lampton Group operating profit for 2025/26 Report P14
  • £6m Savings considered at risk in the budget Report P11

Options considered

  • Chosen: Note the Q1 2026-27 Corporate Risk Register update. Standing quarterly scrutiny of the council's risk exposure Report P1

Implications

  • Financial: The Council must deliver savings and additional funding to bridge the £51.5m 2026/27 budget gap, with a £20m reserve replenishment planned by 2027/28. Report P11, P12
  • Financial: Lampton Group reported a £1.0m operating profit for 2025/26 but recognised an impairment loss; Lampton Investments remains an area of risk. Report P14
  • Financial: School deficits aggregated to £2.5m at end of 2025/26, with a three-year unmitigated forecast of £18m. Report P15
  • Legal: Two Building Safety Regulator cases have been submitted; further information must be provided by December 2026 and Hounslow becomes a collecting authority for the Building Safety Levy from October 2026. Report P3, P4
  • Legal: Following the Regulator of Social Housing inspection, the Council was awarded a C2 and will not face a further inspection for 3 years. Report P5
  • Risk: Cyber security is the highest-scored risk (residual score 16), reflecting rapid changes in attack sophistication driven by AI and supply chain risk. Report P9
  • Risk: Safeguarding of children and extreme weather each scored 15, with safeguarding workforce risk reduced and climate risk increasing in likelihood and consequence. Report P6, P11
  • Staffing: Recruitment and retention of competent building control surveyors remains nationally constrained, with reliance on agency staff at senior levels. Report P4

Who and where

  • Council housing tenants and residents in council properties subject to new building safety requirements Report P3
  • Social housing tenants covered by the new Social Housing Regulation consumer standards Report P5
  • Vulnerable children and adults in Hounslow Report P6, P7
  • Elected members, frontline council staff and community venues, including places of worship, in relation to counter-terrorism security Report P8
  • Council workforce, particularly in Adult Social Care and other hard-to-fill professions Report P9, P10
  • Hounslow residents and businesses exposed to climate change impacts Report P11
  • Maintained schools and the Dedicated Schools Grant (DSG) position Report P15

Timeline

  • Before end of March 2026: Remaining Lampton Group accounts to be signed Report P14
  • Spring 2027: New School Organisation Plan to be considered Report P15
  • September 2026: Updated AI Policy to launch Report P9
  • October 2026: Hounslow Council becomes a collecting authority for the Building Safety Levy; schools to submit financial recovery plans Report P4, P15
  • October half term 2026: All schools to have had at least one financial meeting with the Hounslow Schools' Financial Sustainability Programme Report P15
  • By December 2026: Building Safety Regulator further information to be provided and school recovery plans to be reviewed and agreed Report P3, P15

Plain English for the jargon

  • BSR: Building Safety Regulator, the regulator for building safety
  • RSH: Regulator of Social Housing
  • DSG: Dedicated Schools Grant, the ring-fenced funding for schools
  • MTFS: Medium Term Financial Strategy
  • OHFS: An updated funding settlement referenced for 2026/27 to 2028/29
  • CTLP: Counter Terrorism Local Profile
  • HSFSP: Hounslow Schools' Financial Sustainability Programme
  • Lampton Group: Companies wholly owned by the Council, including Lampton 360 Ltd, Lampton Investment 360 Ltd and Lampton Development 360 Ltd
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4

Resolved

Please see the report by Sarah Filby, Director Strategy, Performance & Commissioning (agenda item 4) The report was presented by Sarah Filby, who drew members’ attention to the salient points and responded to questions.
Word for word from the decision Hounslow published for this meeting. Source: democraticservices.hounslow.gov.uk

Follow this further

Built from Hounslow's papers

What the report saysPro

Report to Audit and Governance Committee

Corporate Risk Register Quarterly Update Q1 to current - Risk Update New Risk ID Risk description Risk type Lead Member Cause and consequence Mitigations CLT Risk Owner Has the nature of the risk (the cause and/ or consequence) Effectiveness of existing mitigations/ current controls Further action - any new mitigations/ Impact Likelihood Q1 2026/27 Direction of Travel What has caused the risk (may be multiple)? changed? controls Residual Risk Score (from previous Q) What are the potential consequences of the risk?

RHES0001 Risk to delivery of regeneration and Transformation & Strategic Delivery Councillor Tom Bruce Inclusive Growth will require significant Ongoing implementation of the Opportunity Executive Director of No Additional controls could be identified through Corporate Plan Significant Possible 12 Medium 0 inclusive growth ambitions regeneration, providing greater business Hounslow: Business Case for Growth. Additional officer Placemaking and Delivery Plan process - performance measures to track progress High opportunities, increased numbers of good jobs and capacity in regeneration and economic growth and Growth homes, improvements to residents’ employment planning teams to promote and enable inclusive prospects, and improvements to the environment growth ambitions. Completing work on Local Plan to and public realm. Failure to deliver these ambitions ensure we have an up to date development plan that limits sustainable, inclusive growth and our enables regeneration, sustainable development and ambitions for the Borough as set out in the growth. Production of masterplans and guidance that Corporate Plan (2026-30) and in Opportunity enables regeneration, development and growth. Focus Hounslow: Business Case for Growth, but is on partnership working with private and public sector, constrained by a very difficult delivery identifying a range of external funding sources, and environment, limited liquidity of key partners and ensuring best use of Council assets. Establishment of a limited resources meaning partnership working is return on investment framework to track delivery and key. performance at regular intervals and preparation of a growth report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260827_CorporateRiskRegisterUpdate_Q12026-27_FINALReport 658 KB DownloadRead as text
PDF
Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)Report 220 KB Download

At this meeting

Whole meeting

Who was there

6 of 8 attended
MS
Councillor Muhammad Shakeel AkramVice-Chair, present
MB
Councillor Marcela BenedettiMember, present
UC
Councillor Unsa ChaudriChair, present
IF
Ilva FoteiniMember, expected
PK
Councillor Parinoor KaurMember, present
NL
Nick LjustinaOfficer, expected
GS
Councillor Gurpreet SidhuMember, present
KS
Councillor Karen SmithMember, present

On this subject at Hounslow

Search all
  1. Quarterly Monitoring of Corporate Risk Register (Q1, 2026-27)This decision
  2. Quarterly Monitoring of Corporate Risk Register - September 2024Noted
  3. Quarterly Monitoring of Corporate Risk Register - March 2024Noted
  4. Quarterly Monitoring of Corporate Risk Register - September 2023Noted
  5. Quarterly Monitoring of Corporate Risk Register - January 2023Noted
  6. Quarterly Performance Monitoring - Q2 2022-23Noted

More from Hounslow Audit and Governance Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Apologies for absence, declarations of interest or any other communication from MembersThere were no apologies for absence, declarations of interest or other communications. Decided Open
8 Sep 2026 Minutes of the meeting held on 3 February 2026The minutes of the meeting held on 3 February 2026 were agreed as an accurate record. Agreed Open
8 Sep 2026 Matters arising from the minutesThere were no matters arising from the minutes. Decided Open
8 Sep 2026 Treasury Management Annual Report 2025/26Please see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 5) The report was pre... Decided Open
8 Sep 2026 Draft Statement of Accounts 2025/26 and External Audit PlanPlease see the report by Jake Bacchus, Executive Director of Finance and Resources (agenda item 6) The report was pre... Decided Open