St Neots Leisure Centre Management Committee: expired April 2009 decided this item on Thursday 5 February 2004. Below is the council's own wording, with the papers it was decided on.
RESOLVED (a) that the Centre Manager be requested to increase supervision by Centre Staff of the facilities throughout the opening hours of the Centre to alleviate potential problems in this area; and (b)that representatives from Ernulf school and the leisure centre meet to discuss a protocol for the use of changing room facilities at the Centre by school children.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to St Neots Leisure Centre Management Committee: expired April 2009
ST. NEOTS LEISURE CENTRE MANAGEMENT COMMITTEE 5th February 2004
MANAGER’S REPORT (Report by the Centre Manager)
1. Performance Indicators 2003/4
Please refer to Annex A.
2. Admissions. ( October – December 2003 )
2002/3 proved to be an exceptional year, with new income and admissions records being set throughout the year. A degree of stabilisation was therefore anticipated for the new financial year. After an initially strong first quarter, the second quarter saw a 5% decrease in admissions. This coincided with substantial duty management staffing changes and probably resulted from the need for the senior management team to become operationally based for a number of months.
Now that the new team has settled in and begun to get to grips with their new, delegated areas of responsibility and the senior management team have resumed normal duties, the third quarter has seen a reduction in falling admissions. The third quarter decrease was just 1.3% over the same period last year, this represents 963 visits, from 76,142 (2002/3) to 75,179 (2003/4).
Year to date figures show that due to the strength of the first quarter, the overall impact of these staffing changes has been less than 0.5% in admissions between April – December, from 241,475 (2002/3) to 240,531 (2003/4). This is particularly encouraging bearing in mind last years record attendances.
2.1Swimming – Public
District wide figures show a slight decrease in both income and admissions, which may largely be explained by the closure of the Ramsey swimming pool for a significant period of time. However, had Ramsey remained open, District wide income would have more closely reflected St. Neots figures which shows the Centre 5% ahead of third quarter target at £83,735, compared to a target of £79,698. Centre admissions figures show a small decrease, year to date, of 1.8% i.e. from 54,398 (2002/3) to 53,390 (2003/4).
From these figures it is clear that the relationship between casual, fee paying admissions and prepaid admissions has changed over the current financial year. This may be linked to the success of the Advantage membership which provides customers with a wider choice of activities to participate in.
2.2Swimming – Lessons Swim lesson income and admissions are above levels set during the same quarter last year, with income up 0.2% and admissions 3.6%.
The lesson programme not only fulfils a customer demand for swim tuition but also fulfils a much needed community service i.e. that of community safety, in an area with many open waterways. This community safety message is being taken a step further by the Swim Steering Group who will soon be launching an educational programme of school visits, aimed at informing children of the dangers of swimming in unsupervised, open water locations.
Following the agreement between Committee partners to allow programming of unused pool time, the Centre is looking into a number of possible extensions to the lesson programme. This should allow greater access to swim lessons to the St. Neots catchment area and fulfil the Centre’s moral, social and financial obligations.
2.3Advantage Memberships and Impressions Fitness Studio
The Impressions Fitness Studio continues to show a reduction in direct income as a result of the popularity of the Advantage packages. Direct Impressions income is down 10% on target with income standing at £58,429 compared with a target of £65,035. This is 7% down on the same period last year, when income stood at £62,910.
In contrast Advantage revenues are over 18% above third quarter target at £105,643 (target being £89,396). Should performance continue at this pace, the year-end target of £127,708 could be attained by the end of February. The main area of Advantage growth has been in the direct debit market where monthly BACS runs now average over £11,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow St Neots Leisure Centre Management Committee: expired April 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Termination of Joint CommitteesRESOLVED (a) that any balance remaining on the repairs and renewals fund on the closure of the separate accounts for ...
Leisure centre management agreementRESOLVED (a) that, subject to the approval of the recommendations in the attached report by the cabinet, a final meet...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.