Sawtry Leisure Centre Management Committee: expired April 2009 decided this item on Wednesday 3 November 2004. Below is the council's own wording, with the papers it was decided on.
RESOLVED that Councillor P G Mitchell be requested to liaise with the District Council’s Head of the Planning Services to seek to resolve the matters of concern and to ensure the project progresses to conclusion in accordance with the scheduled programme. (e) Use of Vending Machines Attention was drawn by the Headmaster to the College’s concern at the use of the vending machines in the Leisure Centre by 6 th form students when pupils had been dis-encouraged as part of a healthy eating initiative, not to eat sweets or chocolate at lunchtime. The Centre Manager undertook to monitor the use of the machines where possible and made reference to the launch of a new scheme in Stevenage entitled “Food for Fitness” which encouraged students to eat healthily to benefit from free sessions at the Leisure Centre. The Committee commended the school and the Centre to consider the introduction of the scheme to the Sawtry site. (f) Condition Survey Members were informed that the majority of work had now been undertaken, including the replacement of the flooring in the wet side changing rooms. (g) Repair and Renewal Fund The Centre Manager reported his intention to improve the provision of indoor cricket facilities at the Centre. The improvements would comprise new cricket nets and the installation of two additional practice bays. It was anticipated that the project would cost £7,800. However, the Centre Manager had secured a grant of £1,000 from the Lords Taverners towards the project subject to the provision of new cricket mats at an additional cost of £1,800. Installation could take place from 29 th November ... view the full minutes text for item 9.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Sawtry Leisure Centre Management Committee: expired April 2009
SAWTRY LEISURE CENTRE 3RD NOVEMBER 2004 MANAGEMENT COMMITTEE
MANAGER’S REPORT (Report by the Centre Manager)
1. PERFORMANCE INDICATORS
Please refer to Annex A.
2. ADMISSIONS
Please refer to Annex A.
Admissions are for the period April 2004 - September 2004 inclusive. The admissions have increased slightly against last year but are still slightly below target however the deficit has been reduced since the August report.
Total Public Admissions are 32,601 compared to the half-year target of 34,100 and compared to last year there is an increase of 1.6% from 32,092.
2.1Swimming - Public
Total swimming admissions (public swimming and lessons) are trailing targets by 4% and currently stand at 19,360. This is just over half way to achieving the annual target of 38,000 although it was expected to be ahead of the 50% at this stage due to the summer holidays.
Income for public swimming alone for the half-year is ahead of target by 3.60% but is behind 03 – 04 by 470 admissions. The pool had to be closed for 4 days at the beginning of September, which explains the 470 admissions and more. The gap between admissions for this year and last year has however improved since the last Management Committee report. The new inflatable fun sessions for children on Wednesdays and Sundays are proving very popular with all sessions reaching maximum capacity.
2.2Swimming - Lessons
Swimming lessons have increased again in the last quarter by almost 10% on the same period last year. Income has improved with an increase in enrolments and exceeds target by 43.58%.
It must be noted that the length of the first two courses of the financial year have both been over 12 weeks. The course that will be offered to customers in January will only be 10 weeks long due to Easter falling in March. Therefore the current excess over target will decrease with the length of the next course. 2.3 Advantage
As always it is a struggle to sell Advantage memberships at SLC but in the last quarter one Direct Debit membership and one Joint Annual membership has been sold.
2.4Vending
Vending income remains below target due to tighter ‘policing’ of the pupils using our vending machines by the College teachers and also the wide range of products available in the school Refectory. Some new ranges of drinks, crisps and sweets have been introduced in to our machines in an attempt to increase sales.
2.5Other (Indoor Activities)
Admissions have improved over the last quarter and have hit targets but income has not risen proportionately. Admissions are 3.4% up on the same period last year but income is over 16% behind this year’s target.
Investigations are under way to cost the running of junior discos that could help boost admission figures.
2.6Synthetic Pitches
Income on the synthetic pitch has improved and is now only 24% behind target. Admissions, however, continue to improve and are currently 23% up on 2003 – 04 figures. The decline in income compared to the increase in admissions reflects the number of junior bookings at the Centre compared to last year’s adult paying bookings.
3. EXPENDITURE
3.1Employees
The savings reported in the July ‘04 report continue to be made by the majority of sickness and annual leave being covered by the Trainee Duty Manager, Deputy Manager and Centre Manager thus eliminating the need to pay overtime.
3.2Premises
Good health and safety management has ensured that operating costs remain lower than target, resulting in a 28% saving, £36.1k compared to the target figure of £50.6k.
3.3Operational – General
Operational costs remain under close scrutiny resulting in a 20% saving.
3.4Operational – Vending
A decrease in vending income is reflected in savings for materials of 44%. 3.5 Net Expenditure
Continued effective control on expenditure has resulted in a current net expenditure saving over 13%, almost £28k.
4. FINANCIAL MONITORING
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Sawtry Leisure Centre Management Committee: expired April 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
Leisure centres activity pricing 2009RESOLVED that the proposed scale of charges as set out the Annex to the report now submitted be approved with effect ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.