Creation of Pedestrian Link between St Germain Walk and High Street, Huntingdon
DecidedPlanning1 paper
Development Control Panel: changed to Development Management Panel - May 2009 decided this item on Monday 15 November 2004. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Council be recommended to request Officers to seek specialist advice regarding the likely level of compensation which might be payable to the landowner should the application for a new right of way be successful and that negotiations continue and the formal views of the landowners, Churchmanor Estates, be obtained on the proposal to re-establish the footpath link.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Control Panel: changed to Development Management Panel - May 2009
AGENDA ITEM NO.
DEVELOPMENT CONTROL PANEL 15 NOVEMBER 2004
CREATION OF PEDESTRIAN LINK BETWEEN ST GERMAIN WALK AND HIGH STREET HUNTINGDON (Report by the Head of Planning & Head of Legal and Estates)
1. INTRODUCTION
1.1The following motion was moved by Councillor T D Sanderson and duly seconded at the Council meeting held on 29 September 2004:
‘that the Development Control Panel be requested to consider the potential options for and the implications of restoring the pedestrian link between St Germain Walk and St Germain Street through to the High Street, Huntingdon.’
1.2Because of the proximity of the Council meeting to the Development Control Panel and the research necessary to prepare a report on the issues raised by the motion, the Development Control Panel at its meeting on 18 October, 2004 agreed to defer consideration of the matter to a future meeting.
2. ST GERMAIN STREET STOPPING UP ORDER
2.1In March 1999 the Secretary of State for the Environment, Transport and the Regions, on the application of the Developer, Churchmanor Estates Company PLC, made an Order under Section 247 of the Town and Country Planning Act 1990 stopping up St Germain Street and a small length of Chequers Way in order to enable the re - development of the town centre in accordance with the planning permission granted by the Council in 1998 under reference 97/1246. A copy of the confirmed Stopping Up Order is attached to this report.
2.2Public notice would have been given by Go-East of the proposal to make the Order and a Notice would have been displayed on the highway itself. There is a 28 day period for objections to be made and the Secretary of State is required to hold a Public Inquiry if any objections are made and not withdrawn. No objection was made to the proposed Closure Order by any public body, private individual or other organisation.
2.3The Secretary of State in confirming the Order, required the Developer to provide an alternative highway along the routes shown by stipple on the Order Plan and for the areas of highway shown cross-hatched to be improved.
3. PLANNING BACKGROUND
3.1The Huntingdon Town Centre Vision undertaken in 2000 identified the Chequers Court area as the most appropriate location in which to expand town centre retail development. A retail needs study carried out in 2001 and commissioned by the District Council identified the need for an additional 5300 square metres of net retail floorspace by 2011. This floorspace is needed to meet identified need and maintain and enhance the vitality and viability of the town. Discussions with Churchmanor Estates started in October 2001 with a view of bringing forward a phase 2 development, now that they had become the owners of the older parts of the Chequers Court development. In January 2003, the Development Control Panel, with the support of the Town Council, approved proposals for the refurbishment of shop units in Chequers Court under planning application reference 02/01699FUL. This permission also authorised:
(i) the provision of a new disabled car park, near the end of Chequers Way;
(ii) improved access (1:20 gradient) for people with disabilities into the southern end of Chequers Court; and
(iii) the erection of the gate at the end of Germain walk next to Wilkinsons' store.
3.2During 2003 and up to April 2004 an Urban Design Framework to guide the new development was produced in association with external consultants and approved for consultation purposes by Cabinet on 6 May 2004. The framework envisaged a retail led scheme with a multi storey car park over the new shops. Access from the High Street to the new development is through an enhanced Chequers Court. An alternative route is through Newton’s Court linking the shops there with the High Street and the new development. A link following the line of St Germain Street had already been legally closed, is in an area where there is likely to be radically changed to accommodate new development, and is on a route of a major service area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.