Centre Manager's Report

Noted Committee 3 papers

Sawtry Leisure Centre Management Committee: expired April 2009 noted this item on Wednesday 27 July 2005. Below is the council's own wording, with the papers it was decided on.

Item12

Resolved

RESOLVED (a) that the Centre Manager be requested to investigate the availability of the pool between 11:40 and 13:10 on Wednesdays and Fridays for 50+ sessions; and (b) that a meeting of the Sawtry Leisure Centre Sub-Group (appointed under Minute No. 08/04) be held in September to discuss the 2005/06 swimming timetable with a view to accommodating the requirements of the primary school, college, leisure centre and local community and a report be submitted thereon to the next meeting of the Management Committee. (c) Extension to Facilities Further to Minute No. 05/7(d), the Leisure Centres' Co-ordinator updated Members on the proposed scheme to extend the Centre to provide a fitness suite and additional car park. In so doing, Members were pleased to note that the bid submitted to Sport England for £206,000 had been successful. Furthermore, the District Council's Cabinet at their meeting on 21st July 2005 had approved a transfer of £59,000 from savings or reductions on other capital schemes involving leisure provision to fund the capital shortfall identified during the tender evaluation process. With regard to a possible start date for the scheme, the Leisure Centres' Co-ordinator reported that work on Phase 1, the relocation of the hard-standing area, was likely to commence in August 2005 and it was hoped that the building work on the Centre’s extension would commence in October with the aim of completing the scheme in May 2006.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Sawtry Leisure Centre Management Committee: expired April 2009

SAWTRY LEISURE CENTRE 27TH JULY 2005 MANAGEMENT COMMITTEE

MANAGER’S REPORT (Report by the Centre Manager)

1. PERFORMANCE INDICATORS

Please refer to Annex A.

2. ADMISSIONS

Please refer to Annex A.

Admissions are for the period April 2005 - June 2005 inclusive. The admissions have increased greatly compared to last year’s actual but trail slightly behind this year’s target. Increases in swimming, both recreational swimming and lessons, indoor sports, fitness classes, sunbed use, junior courses and children’s parties have given the Centre a great start to the new financial year.

Total Public Admissions for the first quarter are 17,688 compared to last year’s figure of 16,012 and the target of 18,830, an increase of 10% but trailing by 2% respectively.

2.1Swimming - Public

Total swimming admissions have reached 6,043 compared to last year’s 5,138 and the target of 5,980.

There has been a rise in recreational swimming right across the board resulting in an overall increase of 18% (905 admissions). The biggest improvement has been adult swimming with an increase of 12% although junior swimming, notorious for fluctuating admissions, has seen a 5% increase. Once again aquafit takes the top award with an increase of 118%, 149 admissions last year to 325 this year. This is a reflection of the daytime aquafit class offered during the summer term which if offered throughout the year would further improve admissions.

Income for public swimming reflects the rise in admissions with a variation on target of +3%.

2.2Swimming Timetable

At the time of writing this report there had been no further communication from Sawtry Community College concerning the allocation of public swimming time throughout the academic year. At the previous meeting SCC informed the Committee that they were ceasing the Wednesday teacher’s swim of 1.0 hour. However this still left an outstanding 1.8 hours (approx 1hr 45mins) still to be allocated. 2.3 Swimming - Lessons

The admissions for the first quarter compare favourably with last years first quarter. The 05 - 06 quarter has exceeded 04 - 05 by 4%, 152 admissions.

The income ‘actual’ figure of £19,390 compares to the target of £18,443 very well, a variation of +5%.

2.4Fitness Suite and Advantage

It is hoped that one day in the not too distant future this element of the Centre Manager’s report will make interesting and exciting reading. Until then the income continues to be nil.

2.5Vending

Income is down by almost 3%, which is surprising considering the improvement in admissions. A complete overhaul of vending provision will shortly be undertaken including a short survey to determine the wants and needs of customers.

The vending profit and vending profit margin compared to a target of 40% are 13% and 27% respectively. However these have both been affected by incorrect coding of original orders by staff at both Ramsey and Sawtry Leisure Centre’s. Accountancy is now aware of the situation but at the time of writing this report the PI’s have not yet been updated.

2.6Other (Indoor Activities)

The improvement in admissions is a result of improvements in badminton 10%, club bookings 15%, fitness classes 35% and junior courses 48%. Further improvement is required to bring junior and adult activities and children’s parties up to expected targets.

The first quarter income shows a healthy variation of £21,084 compared to the target of £19,829, an additional 6%. Overall, admissions have increased by 14% on 04 - 05 and exceeded 05 - 06 targets by 16%.

2.7Synthetic Pitch (MAA)

Admissions for the MAA in the first quarter were expected to be low due to the end of the football season and an early Easter that led to club bookings finishing earlier than normal. This has been reflected in admissions falling from 1,518 to 1,143, a drop of 25%. Income shows a variation of –44%.

All football clubs in the catchment will be contacted in early August to inform them of the available facilities at SLC. 3. EXPENDITURE

3.1Employees

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Az SLC Mgt Rep Annex A Jul 05Appendix 58 KB Download
PDF
Az SLC Mgt Rep Annex B Jul 05Appendix 22 KB Download
PDF
Centre Manager's ReportReport 23 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 12 attended
MM
Councillor Mrs Madhabi BanerjeeChair, present
SB
Simon BellNon-elected, voting, in attendance
MJ
Councillor Mrs Jean ChandlerMember, present
PC
Peter CorleyOfficer, in attendance
CD
Christopher DavidsonNon-elected, voting, in attendance
JD
Mrs J DayNon-elected, voting, present
JE
Councillor John Edward GarnerVice-Chair, present
SM
Sue MartinOfficer, in attendance
PG
Councillor Peter Gerald MitchellMember, present
HT
Mrs Helen TaylorSecretary, in attendance
RG
Councillor Richard Graham TuplinNon-elected, voting, present
JS
Councillor John Samuel WattMember, present

On this subject at Huntingdonshire

Search all
  1. Centre Manager's ReportThis decision
  2. Centre manager's reportDecided
  3. centre manager's reportDecided
  4. Centre manager's reportDecided
  5. Centre manager's reportApproved
  6. Centre manager's reportApproved

More from Huntingdonshire Sawtry Leisure Centre Management Committee: expired April 2009

All decisions
MeetingDecisionOutcome
4 Feb 2009 2008/09 Revenue Monitoring & 2009/10 Revenue BudgetRESOLVED that the revised outturn for 2008/09 and the budget for 2009/2010 together with the proposed allocation of n... Approved Open
23 Jul 2008 Final outturn 2007/08RESOLVED (a) that the outturn position for 2007/08 be noted; (b) that the Annual Governance Statement and Annual Retu... Noted Open
23 Jul 2008 Leisure centres' annual reportRESOLVED that the contents of the Leisure Centre’s Annual Report for 2007/08 be received and noted. Noted Open
23 Jul 2008 Swimming direct debit pricingRESOLVED that the charge for swimming lessons be increased from £14.00 to £15.50 per month per child, from 1 st Septe... Decided Open