ODPM CIRCULAR 08/2005 GUIDANCE ON CHANGES TO THE DEVELOPMENT CONTROL SYSTEM
NotedPlanning1 paper
Development Control Panel: changed to Development Management Panel - May 2009 noted this item on Monday 19 September 2005. Below is the council's own wording, with the papers it was decided on.
RESOLVED (a) that the revised guidance in respect of changes to the development control system be noted and the proposed operational responses endorsed; and (b) that appropriate Officers be requested to advise town and parish councils on the need to adjust if necessary, their arrangements for responding to planning applications and to offer guidance to local councils in complying with these requirements in terms of the holding of meetings for that purpose.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Control Panel: changed to Development Management Panel - May 2009
AGENDA ITEM NO.
DEVELOPMENT CONTROL PANEL 19 SEPTEMBER 2005
ODPM CIRCULAR 08/2005 – GUIDANCE ON CHANGES TO THE DEVELOPMENT CONTROL SYSTEM (Report by the Head of Planning Services)
1. INTRODUCTION
1.1The purpose of this report is to inform the Panel of the proposed/implemented changes to the development control system and to consider the related implications for the operations of the development control service.
2. BACKGROUND INFORMATION
2.1As Members will be aware the Government has been pursuing a policy of implementing changes to the form and nature of the planning system since the enactment of the Planning and Compulsory Purchase Act 2004.
2.2ODPM Circular 08/2005 was published on 24 August 2005 in order to provide guidance regarding the changes to the development control system. A copy of the Circular is attached for Members information.
3. IMPLICATIONS FOR THE OPERATION OF THE DEVELOPMENT CONTROL SYSTEM
3.1As Members will be able to ascertain the Circular provides updated guidance in respect of four specific aspects of the development control system.
Power to Decline to Determine Applications
3.2The Government has been concerned regarding situations whereby applicants have continuously submitted applications in order to try and wear down local opposition to their proposals. Therefore Paragraphs 3 to 18 of the Circular explain the basis of the enhanced powers available to local planning authorities to decline to determine such repeat applications. In essence the changes build upon the existing provisions to allow local planning authorities to be able to decline to determine ‘similar applications’ which have been subject to a previous refusal (but which has not been appealed) within the last two years. Members should be aware that there is no right of appeal against the planning authority pursuing this course of action but an applicant could apply for a judicial review of an authority’s decision.
Duration of Permission and Consent
3.3The Government has also been very concerned about developers sitting on their land holdings rather than actually going on to develop their permitted sites. Accordingly Paragraphs 19 to 33 provide guidance in respect of the legislative changes relating the duration of permissions and consents. In essence the previous time limit of five years to implement a planning permission has been reduced to a maximum of three years (and the capacity to extend those time limits is to be removed) in order to positively encourage the active implementation of permissions.
Duty to Respond to Consultation
3.4As Members will be aware the Government now places great emphasis upon the need for local planning authorities to determine applications expeditiously. Accordingly as part of the determination process greater emphasis is now being placed upon the need for statutory consultees to response to planning consultations within set time periods. The revised guidance in Paragraphs 34 to 56 sets out the requirement for statutory consultees to respond within 21 days of receiving the consultation (and to subsequently report upon their compliance with these targets). Obviously these changes may have some implications for our Parish and Town Councils (which are statutory consultees for planning purposes). Accordingly it is my intention to write to all of our Parish and Town Councils to remind them of the time limits being imposed upon them and the need for their response mechanisms to be tailored towards being able to respond appropriately.
Consultation with Regional Planning Bodies
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.