Resolved
RESOLVED that the outcomes of the Annual Monitoring Report be noted.
Development Control Panel: changed to Development Management Panel - May 2009 noted this item on Monday 20 February 2006. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the outcomes of the Annual Monitoring Report be noted.
2.1It is a requirement of the Planning and Compulsory Purchase Act 2004 that the Council reports to the Secretary of State, by means of an Annual Monitoring Report, the progress that has been made in preparing development plan documents over the previous financial year. The Local Development Framework should be constantly reviewed and revised, and the AMR will be the main mechanism for assessing the framework’s performance and effects.
3 REQUIREMENTS OF THE ANNUAL MONITORING REPORT
3.1The Town and Country Planning (Local Development) Regulations 2004 set out the requirements for the Annual Monitoring Report. The report must:
1. contain information about the implementation of the Local Development Scheme
2. set out the extent to which policies in Local Development Documents are being achieved
3. identify any policies that are not being implemented, giving reasons why, and what steps are to be taken to secure their implementation if necessary
4. report on the net additional dwellings that have been built in the District
3.2The Government has published a document ‘Local Development Framework Monitoring: A Good Practice Guide’ which gives guidance on how an Annual Monitoring Report should be prepared, and suggesting a set of Core Output Indicators to use as a framework for the monitoring of policy implementation. This guidance has been taken into consideration in the preparation of the first AMR. 4 SUMMARY OF THE CONTENT OF THE AMR
4.1This is the first AMR to be prepared. As no Local Development Documents were in effect during the monitoring period, this AMR focuses on the following:
• Local Development Scheme (LDS) progress
• Identifying indicators and establishing a framework for monitoring Local Development Documents
• Analysis of non-implementation of existing policies
• Housing trajectory showing past performance and estimating future performance in terms of housing delivery
4.2Progress in the LDS is measured against ‘key milestones’, which are key stages in the production of documents. Although the AMR relates to the year ending 31 March 2005, it is regarded as best practice to give an update on progress against the most recent LDS. As at December 2005, all key milestones in the LDS dated September 2005 had been achieved, indicating that the Council is on track with regard to its preparation of documents.
4.4A table of indicators has been identified, which link with the spatial objectives set out in the Core Strategy: Preferred Options Report, and the sustainability appraisal objectives in the Sustainability Appraisal Scoping Report. These indicators will be reviewed and may be added to as Development Plan Documents are adopted and new policies come into effect, or as more data become available. These indicators will enable analysis of policy implementation and the progress being made towards related targets.
4.5A table of policies which are no longer being implemented is included, together with reasons why, and, if applicable, what steps the Council intends to take to secure their implementation. A number of retail and transport policies have been superseded by Government guidance.
4.6The housing trajectory shows the current position regarding housing delivery in Huntingdonshire, with a forecast of future supply. It compares levels of actual and projected housing completions with the strategic housing requirement, in order that any shortfall or surplus in supply can be identified, and if necessary housing policies can be reviewed. This trajectory shows that Huntingdonshire is currently performing well in the delivery of its annual housing requirement, and no shortfall in delivery is anticipated.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
LOCAL DEVELOPMENT FRAMEWORK: ANNUAL MONTIORING REPORTReport | 13 KB | DownloadRead as text |
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Apr 2009 | Development controlRESOLVED (a) Erection of four floodlight columns and floodlights, informal open space, north-east of 46 High Street ,... | Approved | Open |
| 16 Mar 2009 | Development controlRESOLVED (a) Removal of Condition 9 of Reserved Matters Approval 07/02174/REM to allow floodlighting, land at Gifford... | Approved | Open |
| 16 Mar 2009 | S106 agreement advisory groupRESOLVED that Councillor J S Watt be appointed to the vacancy in the membership of the Section 106 Agreement Advisory... | Agreed | Open |
| 16 Mar 2009 | Exclusion of press and publicRESOLVED that the public be excluded from the meeting because the business to be transacted contains exempt informati... | Agreed | Open |
| 16 Mar 2009 | Change of use to gypsy site without planning permission, land 800 metres east of woodwalton nature reserve and south of harpers drove, ramsey heights, huntingdon - 09/00038/encaraRESOLVED that the approach outlined in the report now submitted be endorsed, namely the issuing of an enforcement not... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.