Resolved
RESOLVED (a) that the contents of the report be noted; and (b) that an update on the Headquarters and Other Accommodation Project be presented to the meeting of the Panel in September 2007.
Overview and Scrutiny Panel (Corporate and Strategic Framework): 2006-09 - transferred to Economic Well Being noted this item on Tuesday 30 January 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (a) that the contents of the report be noted; and (b) that an update on the Headquarters and Other Accommodation Project be presented to the meeting of the Panel in September 2007.
OVERVIEW & SCRUTINY PANEL 30 JANUARY 2007 (CORPORATE AND STRATEGIC FRAMEWORK)
ACCOMMODATION PROJECT AND TRAVEL PLAN UPDATE (Report from Head of Technical Services)
1 INTRODUCTION
1.1This report provides Members with the current position with regard to the Headquarters and Other Accommodation Project. It also provides the latest position with regard to arrangements for parking during the delivery of the project and a commentary on the implementation of the Council’s Travel Plan.
2 NEW ACCOMMODATION - PROCUREMENT
2.1Following the decision of the Council at its meeting in February 2006 to appoint Alfred McAlpine Capital Projects as the preferred bidder for the new accommodation there followed a period of intense negotiation to conclude the Development Agreement. The agreement, which was signed on 10 November 2006, established the contractual relationship between the Council and McAlpine.
2.2The agreement provides for –
• the construction of a new Operations Centre on land purchased by the Council; • the redevelopment of the Pathfinder House site to provide a new customer service centre, offices and public meeting rooms for the Council; • the disposal of Castle Hill House; • the provision of temporary accommodation necessary to maintain the council’s services during the construction of the new accommodation; and • the clearance of the existing Godmanchester Depot site.
2.3The contract value is capped at £20.523 million and includes provision for any savings to be shared on a 50/50 basis between the Council and McAlpine. It also assumes a net receipt from the disposal of Castle Hill House of £0.98 million.
2.4The Operations Centre, which will replace Godmanchester Depot and its satellites in St Ives, St Neots and Huntingdon, is to be constructed on 3.43 acres of land at Latham Road, Huntingdon, purchased from St John’s College. The total acquisition cost inclusive of associated agreements, taxes and fees amounted to £1.8 million.
2.5The Development Agreement includes a provision for the construction only of the Operations Centre in any circumstance where the headquarters cannot be delivered. Should this arise the construction cost is capped at £4.625 million 3 NEW ACCOMMODATION – CONSTRUCTION
3.1Construction of the Operations Centre, to be known as Eastfield House, started in December 2006 and is programmed for completion in July 2007.
3.2A planning application has been submitted for the headquarters buildings and the temporary accommodation to be used for decanting purposes. It is anticipated that this will be determined by the Development Control Panel at their meeting in March 2007.
3.3Building work on the headquarters site will commence in September 2007 with the preparatory work necessary to allow part of Pathfinder House to be demolished. New construction will start in November 2007 with Building D, the block facing the ring road, followed shortly after by Building A which faces St Mary’s Street. An archaeological investigation will have to be completed before construction can start and this is programmed to commence in March 2007.
3.4Following the occupation of the first Buildings A and D the remainder of Pathfinder House will be demolished and the next phase of construction will start in January 2009. Final occupation of the new headquarters is programmed for February 2010.
3.5It is expected that a planning and listed building consent application in respect of Castle Hill House will be submitted in March 2007. Once the necessary consents have been secured a nine-month marketing period will commence with a view to securing a disposal for residential conversion with vacant possession after the new headquarters is finally occupied.
3.6Godmanchester Depot also will be demolished in early 2010 and will be available for disposal or alternative uses.
4 OPPORTUNITIES
4.1Business Link will be vacating Centenary House before April 2007. If the lease of this building, located at the junction of St Mary’s Street and the ring- road, could be secured it provides an opportunity to –
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Headquarters UpdateReport | 18 KB | DownloadRead as text |
Follow Overview and Scrutiny Panel (Corporate and Strategic Framework): 2006-09 - transferred to Economic Well Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jan 2009 | Financial strategy, medium term plan 2010 to 2014 and the 2009/10 budgetIt was agreed that the Working Group should take into account which items within the budget were a statutory requirem... | Agreed | Open |
| 27 Jan 2009 | 2009 / 10 treasury management strategyRESOLVED that the Cabinet be requested to recommend the Council to adopt the revised Treasury Management Strategy. | Approved | Open |
| 27 Jan 2009 | Exclusion of the publicRESOLVED that the public be excluded from the meeting because the business to be transacted contains exempt informati... | Decided | Open |
| 2 Sep 2008 | Growing success - corporate planRESOLVED that the Corporate Plan - Growing Success be endorsed for submission to the Cabinet and Council. | Decided | Open |
| 2 Sep 2008 | Financial forecastRESOLVED that the report now submitted be endorsed for submission to the Cabinet and Council. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.