RESOLVED (a) that the report and potential implications for the Council of the “Standards Authority” designation be noted; (b) that the procedural and operational changes set out in paragraph 4.2 of the report now submitted be strongly endorsed and implemented with immediate effect; (c) that the Panel continue to monitor both the performance of the Development Control Section and evaluate the scope for further performance enhancements should these be necessary; and (d) that the views of the Panel in respect of recruitment issues in the Development Control Section be conveyed to the Cabinet and the Employment Panel.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Control Panel: changed to Development Management Panel - May 2009
AGENDA ITEM NO.
DEVELOPMENT CONTROL PANEL 18 JUNE 2007
DESIGNATION AS BEST VALUE PLANNING AUTHORITY FOR MAJOR APPLICATIONS FOR 2007/8 AND PERFORMANCE IMPROVEMENT PLAN (Report by the Development Control Manager)
1. INTRODUCTION
1.1The purpose of this report is two-fold, firstly to inform the Panel that the Council, acting in respect of its role as the Local Planning Authority, has as had been anticipated now formally been designated as a ‘standards authority’ for Major Applications for 2007/08 and, secondly, to therefore seek the Panel’s endorsement of a Performance Improvement Plan to ensure that the targets for determining major applications in particular are met.
1.2Those Members on the Panel in December will remember that you considered a report at that meeting advising you that the Council had been designated as a potential ‘standards authority’ for Major Applications in 2007/08. At that meeting, amended and enhanced procedural arrangements, and operating practices, in order to allow the Council to increase its effectiveness and efficiency in terms of the ways in which it determines major planning applications were endorsed.
1.3The agreed procedural and operational enhancements were:
• The planning application registration process is made even more stringent in order to ensure that all of the required essential information, which will be necessary for the Council to appropriately deal expediently with the planning proposal, is submitted with the application. In relation to this measure the Council will continue to upgrade, update and enhance its guidance to potential applicants in order to ensure that they are fully aware of the standard of application submission that will be required from them.
• That all the applicable administrative procedures and processes (right through from the submission of an application to decision making) are reviewed in order to look for further deliverable increases in efficiency. This may include reviewing current performance management systems and the use of process mapping to identify and remedy any discernable blockages within the determination process.
• That detailed consideration be given to further enhancing our existing pre-application advice service, which due to other operational necessities has had to be considered a lesser priority, in order that potential applicants can be advised about what will be required in order to constitute an appropriate submission, that good design and other environmental improvements can be encouraged and significantly that inappropriate planning proposals can be effectively discouraged prior to any formal submission.
• That the Council positively considers making use of more standardised Section 106 Agreements, and other forms of planning obligations, in order to try and fast track the negotiation processes which can extend the life of a major application way beyond its required decision date. Major applications, by their very nature, obviously give rise to the need for complex Section 106 Agreements, and in conjunction with the on-going work in respect of the emerging Planning Obligations Development Plan Document, additional detailed thought will be given to the viability of requiring proactive pre- application negotiations.
• That the scheme of delegation for the determination of planning applications is again reviewed in order to ensure that it is operating efficiently and effectively both in terms of what type of application the Development Control Panel is focussing is on dealing with and to ensure that all avoidable processing delays are minimised wherever possible. As Member’s will be aware national best practice strongly advocates that the Development Control Panel should target its limited time resources at dealing with those major and controversial applications that could have a significant impact upon the character of Huntingdonshire.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.