Resolved
RESOLVED that the outturn position for St Neots Leisure Centre in 2006/07 be noted.
St Neots Leisure Centre Management Committee: expired April 2009 noted this item on Thursday 26 July 2007. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the outturn position for St Neots Leisure Centre in 2006/07 be noted.
ST. NEOTS LEISURE CENTRE 26th JULY 2007 MANAGEMENT COMMITTEE
FINAL ACCOUNTS 2006/07 AND BUDGET MONITORING 2007/08 (Report by the Treasurer)
1 INTRODUCTION
1.1This report summarises the Centre’s final accounts for last year (2006/07) and comments on any significant variations from the budget. It also considers any variations that are emerging in the current year.
2. FINAL ACCOUNTS 2006/07
2.1As shown in the table below, net expenditure was £69k lower than the budget.
Original Final Variation Budget Outturn to Orig £’000 £’000 £’000 Expenditure - Managers Responsibility 1,127 1,098 -29 Impressions 129 123 -6 Indirect 437 441 +4 Total Expenditure 1,693 1,635 -31 Income – Managers Responsibility 650 677 +27 Impressions 291 287 -4 From Partners 87 102 +15 Total Income 1,028 981 +38 Net Expenditure Funded by HDC 665 654 -69
2.2The main variations are shown in the summary section on the first page of Annex A. Items outside the direct control of the Centre Manager and the Impressions Brand Manager (Inflation on fuel costs, capital charges, central support charges, irrecoverable VAT, pension liability, NNDR charges and part of the identified savings) rose by £26k, however, the Centre Manager and Impressions Brand Manager produced savings that off-set these increases.
2.3The Centre Manager and the Impressions Brand Manager now have clearly defined responsibility for budgets at the centre. Last year the Centre Manager made savings against the staffing budget (£41k) increased income (£27K), this was partially off-set by increases on equipment and other expenditure. 2.4 When the 2007/08 budget report was considered back in February, Impressions was expected to outturn slightly over budget. Impressions actually under spent by £2k with savings on staffing (£10k) but increased expenditure on equipment (£4k) and a slight reduction in income (£4k).
2.5The cost share calculation picked up the additional NNDR charges and the higher fuel costs other changes and resulted in an additional £15k contribution from partners being due. However, part of this increase (£5k) does relate to 2005/06.
2.6Whilst St. Neots Leisure Centre was able to achieve the budget targets with apparent ease again, this was partly due to the historic deferring of expenditure because of the uncertainty of the future plans for the site. This is unlikely to continue into 2007/08 because of planned repairs/improvements in particular to the pool building.
2.7Annex B shows a summary of the position on all Centres which highlights additional net spending of only £17k over all the centres. This is despite irrecoverable VAT charged to the Centres adding an extra £85k to expenditure, fuel costs adding £41k to expenditure and items outside the direct control of the Centre Managers (capital charges, NNDR charges and Central Support charges) adding £73k to expenditure.
2.8Following on from last year, information on Capital Charges and Central Support Charges have been included in Annex C and Annex D to this report.
3. APPROVAL OF THE FORMAL SET OF ACCOUNTS
3.1As reported elsewhere on the agenda, the Accounts Committee th approved the Statement of Accounts at their meeting on 27 June 2007 and they have been submitted for audit. A further meeting of the sub- committee will be required in September to approve the Annual Statement of Assurance on Corporate Governance once it is completed.
3.2If any significant matters are identified by the auditor the accounts must be reported back to the Management Committee, or an appointed sub- committee, before the accounts can be published. The accounts must be published by 30 September.
4. CURRENT YEAR
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FINAL OUTTURN 2006/07Report | 145 KB | DownloadRead as text |
Follow St Neots Leisure Centre Management Committee: expired April 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2009 | Termination of Joint CommitteesRESOLVED (a) that any balance remaining on the repairs and renewals fund on the closure of the separate accounts for ... | Decided | Open |
| 12 Feb 2009 | Leisure centre management agreementRESOLVED (a) that, subject to the approval of the recommendations in the attached report by the cabinet, a final meet... | Approved | Open |
| 23 Oct 2008 | Final Accounts Update 2007/08RESOLVED (a) that the Annual Governance Statement and the Letter of Representation be formally approved and signed by... | Approved | Open |
| 23 Oct 2008 | Free SwimmingRESOLVED that the contents of the report submitted be noted. | Noted | Open |
| 24 Jul 2008 | Final accounts 2007/08 and budget monitoring 2008/09RESOLVED that the final outturn position for 2007/08 and the current expected variations for 2008/09 be received and ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.