CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Huntingdonshire District Council
Corporate Governance Panel, Wednesday 12 December 2007 at 6.00pm

INTERNAL AUDIT SERVICE - CHANGING REPORTING PERIODS

Decided Committee 1 paper

Corporate Governance Panel decided this item on Wednesday 12 December 2007. Below is the council's own wording, with the papers it was decided on.

Item22

Resolved

RESOLVED (a) that the audit plan year be based on August to July; (b) that an audit plan for four months ending July 2008 be presented to the March meeting of the Panel; and (c) that the Internal Audit Strategy be amended to reflect the change in reporting period.
Word for word from the decision Huntingdonshire published for this meeting. Source: democracy.huntingdonshire.gov.uk

Follow this further

Built from Huntingdonshire's papers

What the report saysPro

Report to Corporate Governance Panel

CORPORATE GOVERNANCE PANEL 12 DECEMBER 2007

INTERNAL AUDIT SERVICE CHANGING REPORTING PERIODS

(Report by the Audit & Risk Manager)

1. INTRODUCTION

1.1Internal Audit annual plans have historically been prepared around the financial year (April to March). This report proposes that the audit year is changed to August/July, so that the reporting of the delivery of the audit plan and associated reports fits more closely to the governance reporting timetable.

2. REPORTING PERIODS

2.1A core set of reports are required to be presented to the Panel over a twelve month period. In particular the annual internal report and opinion is reported to the September meeting in order to coincide with the Corporate Governance Statement. This report considers the audits that have taken place in the 12 months to the end of July. It therefore seems illogical to continue with two separate audit plan years – April to March for administrative purposes and August to July for corporate governance purposes. It is therefore proposed that the audit plan year is changed so that it covers the period August to July.

2.2Thus the September report will report on audit achievement for the year and an interim report on progress will be reported to the March meeting covering the half year from August to January.

2.3Annex A outlines an amended reporting timetable. If the proposals are agreed, minor changes will be required to the audit strategy to reflect these amended timings.

2.4The external auditor has been consulted over the proposed changes and has raised no objections.

3. EXTENDING THE 2007/08 AUDIT PLAN

3.1If it is agreed that the audit plan should cover the period August to July, then it is proposed that the current 2007/08 audit plan be ‘extended’ by four months to run to July 2008. The additional audits will be reported to the Panel’s March meeting and then the audit year proposals for August 2008 to July 2009 will be reported to the June meeting.

4. DELIVERY OF THE 2007/08 AUDIT PLAN

4.1Progress in delivering the 2007/08 plan up to the end of July was included in the September report. Since then progress has been good and the March meeting will receive the first half-year monitoring report based on the “new” year – August 2007 to January 2008.

4.2Electronic copies of all completed reports are available to Members on the Internal Audit intranet home page. 5. RECOMMENDATION

It is recommended that:

• the audit plan year be based on August to July. • an audit plan for the 4 months ending July 2008 be presented to the March meeting of the Panel • the Internal Audit Strategy should be amended to reflect this change

BACKGROUND INFORMATION Internal audit strategy Internal audit & assurance plan 2007/08

Contact Officer: David Harwood, Audit & Risk Manager ( 01480 388115 Annex A

Audit & Risk Reports to the Corporate Governance Panel 2008 2009 2010

March

March

March June

June Sept

Sept Dec

Dec Report to be submitted Reporting period to be covered

AUDIT PLAN 2007/08 Audit Plan extension April 2008 to July 2008 ü ½ year audit progress report August 2007 to January 2008 ü Annual audit report & opinion August 2007 to July 2008 ü

2008/09 Annual Audit Plan 2008/09 August 2008 to July 2009 ü ½ year audit progress report August 2008 to January 2009 ü Annual audit report and opinion August 2008 to July 2009 ü

2009/10 Annual Audit Plan 2009/10 August 2009 to July 2010 ü ½ year audit progress report August 2009 to January 2010 ü

ANNUAL REVIEWS Review of internal audit’s terms of reference ü ü Annual Review of the effectiveness of Internal Audit ü ü Anti-fraud & corruption policy review ü ü Whistleblowing policy review ü ü

UPDATES Risk Management update ü ü ü ü ü March

March

March June

June Sept

Sept Dec

Dec

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
INTERNAL AUDIT SERVICE: CHANGING REPORTING PERIODSReport 69 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 7 attended
KJ
Councillor Ken James ChurchillVice-Chair, present
PJ
Councillor Peter James Downes OBEMember, present
JA
Councillor Jonathan Alexander GrayMember, apologies
TV
Councillor Terence Victor RogersMember, present
LM
Councillor Lawrence Michael Simpson(known as Mike)Member, present
CJ
Councillor Christopher John StephensChair, present
GS
Councillor Gordon Sydney Edward ThorpeMember, present

On this subject at Huntingdonshire

Search all
  1. INTERNAL AUDIT SERVICE - CHANGING REPORTING PERIODSThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit Actions UpdateNoted
  4. Internal Auditor's Annual Report - Including Head of Internal Audit Opinion 2025/26Noted
  5. Internal Audit Progress ReportNoted
  6. Draft Internal Audit Plan for 2026/27 and Internal Audit CharterNoted

More from Huntingdonshire Corporate Governance Panel

All decisions
MeetingDecisionOutcome
9 Mar 2016 Appointment of vice-chairmanRESOLVED that Councillor T Alban be appointed as the Vice-Chairman of the Corporate Governance Panel for the remainde... Decided Open
9 Mar 2016 External audit plan 2015/16RESOLVED that the Panel notes the content of the revised External Audit Plan for 2015/16 and agrees with the level of... Agreed Open
9 Mar 2016 Grant certification 2014/15RESOLVED that the Panel note the content of the External Auditor’s Annual Certification Report 2014/15. Noted Open
9 Mar 2016 Internal audit service: internal audit plan 2016-17RESOLVED to approve the Internal Audit Plan for 2016/17. Approved Open
9 Mar 2016 Accounting policies for the annual financial report 2015/16RESOLVED to approve the amendments to the accounting policies for the Annual Financial Report 2015/16 as listed in Ap... Approved Open