PLANNING APPLICATION CONSULTATION - CREATION OF THE NEW TOWN OF NORTHSTOWE AND ASSOCIATED COMMUNITY AND HIGHWAY INFRASTRUCTURE WORKS
DecidedPlanning1 paper
Development Control Panel: changed to Development Management Panel - May 2009 decided this item on Monday 25 February 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED (a) that South Cambridgeshire District Council be advised that the District Council offers its support for and early delivery of the proposed development of a new town at Northstowe ; and (b) that, South Cambridgeshire District Council be encouraged to require, by condition, the submission of a construction traffic access scheme and in the event that such a scheme is provided, that the District Council be invited to participate in any consultation on the scheme content.
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Control Panel: changed to Development Management Panel - May 2009
AGENDA ITEM NO.
DEVELOPMENT CONTROL PANEL 25 FEBRUARY 2008
PLANNING APPLICATION CONSULTATION – CREATION OF THE NEW TOWN OF NORTHSTOWE AND ASSOCIATED COMMUNITY AND HIGHWAY INFRASTRUCTURE WORKS (Report by the Head of Planning Services)
1. INTRODUCTION
1.1The purpose of this report is to inform the Panel that the Council has been formally consulted by South Cambridgeshire District Council, SCDC, who are the applicable Local Planning Authority, with regard to the submitted planning applications relating to the proposed development of the new town of Northstowe.
2. BACKGROUND INFORMATION
2.1The proposed development of a new town on this site has already been approved in ‘principle’ by RPG6 and the Cambridge Sub- Regional Study and it was formally allocated by the adopted Cambridgeshire and Peterborough Structure Plan 2003 and the SCDC Core Strategy 2007. Therefore these current proposals constitute an outline application for the creation of the new town and for the related new roads and road improvements (to both access the site and to improve the local junctions with the A14).
2.2The planning application for the new town proposes that some 427ha of land be developed; for residential purposes (delivering approximately 9,500 new homes with a planned population of some 24,000 new residents), to create new employment opportunities (for approximately 9,000 new jobs), and to deliver a new town and local centres (including retail developments), new schools, play and amenity spaces. It is intended that the retail offer in the town centre will develop over a period of 12 years from an initial foodstore to provide a range of comparison and convenience shopping equivalent to the space provided in a typical market town.
2.3The Cambridge to Huntingdon Guided Bus will pass through the site and provide for a strategic sustainable transport link.
3. IMPLICATIONS FOR HUNTINGDONSHIRE
3.1The successful delivery of the proposed new town development at Northstowe is considered to be a key element of the approved and adopted growth strategy for the Cambridge Sub-Region. The further delayed implementation of this part of the strategy would obviously place increasing pressures upon the surrounding districts to potentially accommodate additional growth. Accordingly it is considered important for the validity of the Huntingdonshire Core Strategy, specifically in terms of the ability of the district to readily accommodate the already implied levels of growth and for us not to be faced with unsustainable additional demands, that the development of Northstowe is now readily expedited. Therefore it is recommended that the Council offers positive support for the early delivery of the new town.
3.2Having regard to the details of the proposed development it is considered that there are two specific areas that may have further implications for Huntingdonshire:
• Both established policy and the proposed transport and vehicle access strategy proposes that the development is appropriately phased to ensure that sufficient highway capacity is available within the A14 corridor, to deal with the traffic generated by that phase, and that the guided bus scheme is successfully implemented. It will be important, to successfully mitigate the traffic impacts of the development, that both of these requirements are effectively complied with.
• Two Preferred Route Announcements have now been made by the Highways Agency relating to the A14 improvements with a view to starting construction late in 2010. In the vicinity of Northstowe, this will include a 3-lane dual carriageway from Fenstanton to the Girton interchange, limited junctions on the A14 and a parallel distributor road or roads for local traffic linking to the vehicle access strategy for the development
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.