ENFORCEMENT ACTION - UNAUTHORISED CONTINUATION OF USE OF WOODSHAVING LINE, SUNDOWN STRAW PRODUCTS, STATION ROAD, TILBROOK
ApprovedPlanning1 paper
Development Control Panel: changed to Development Management Panel - May 2009 approved this item on Monday 19 May 2008. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Head of Legal and Estates be authorised to take appropriate enforcement action to secure the cessation of the woodshaving line operation at Sundown Straw Ltd, Station Road, Tilbrook or the implementation of the access arrangement approved in planning consent 06/03767/FUL or implementation of the access arrangement approved in planning consent 07/04009/FUL within six months of the date upon which the enforcement notice is served. [The Panel noted the content of written representations which had been circulated on behalf of Councillor J A Gray.]
Word for word from the decision Huntingdonshire published for this meeting.Source: democracy.huntingdonshire.gov.uk
Report to Development Control Panel: changed to Development Management Panel - May 2009
Purpose of report
1.1This report is to inform Members of the continued use of the woodshaving line at Sundown Straw, following the refusal of application reference 0702972S73, which sought consent for the continuation of the use and extension of time for the delivery of the proposed new access road, and to seek Members’ authority for enforcement action to be taken.
2. DESCRIPTION OF SITE AND ITS CURRENT USE
2.1This site is well known to Members, located within the open countryside to the south of Catworth. It lies to the west of Station Road (B660) and is adjacent to the former railway station. Access to the site is from the B660 via a shared access with The Station House. Adjacent to this access is a row of residential properties fronting the B660.
2.2As Members are aware planning permission was granted in 1974 for a chemical straw plant, which has been extended over the years (74/00217FUL). In 1997 planning permission was granted for an additional straw processing plant (97/101368 FUL). Further permissions include the erection of a building for the storage of straw, 3 storage silos and intake canopy (98/01545FUL) and an extension to a warehouse (0200897FUL).
2.3Between October 2005 and September 2007 a further four temporary planning permissions (including one S73 application) have been granted for two additional uses on the site, two full planning permissions, one of which was for a further additional use and one full planning permission for an additional building and a new road layout.
2.4In January 2008, the owner of the site submitted a further planning application for an amended revised road layout and obtained full planning permission. HUNTINGDONSHIRE DISTRICT COUNCIL
2.5At this time, the owner of the site is operating the chemical straw plant for straw processing (includes two processing plants) and the woodshaving line with extant permissions for a baling plant for the processing of straw, hay and dried grass and the manufacture of wood pellets.
2.6The site also benefits from two extant permissions for a new access road.
3. PLANNING HISTORY
3.1Planning permission was granted in 1974 for a chemical straw plant, which has been extended over the years (74/00217FUL). In 1997 planning permission was granted for an additional straw processing plant (97/101368 FUL). Further permissions include the erection of a building for the storage of straw, 3 storage silos and intake canopy (98/01545FUL) and an extension to a warehouse (0200897FUL).
3.2In October 2005, a temporary, 12 month permission was granted for the installation of a wood shavings line and chimney (0502662FUL).
3.3In January 2006, permission was granted for the erection of a dust fired burner- 0503890FUL.
3.4In March 2006, a temporary 12 month permission was granted for the change of use and extension to warehouse to house baling plant to process straw, hay and dried grass. – 0600428FUL
3.5In November 2006, a further 12 month temporary permission was allowed for the woodshaving line (0603089FUL).
3.6In March 2007, Members approved the erection of building to be used as additional storage, new road layout to existing access/egress and improvements to access/egress on Station Road (0603797FUL).
3.7In May 2007, a further 12 month temporary permission was allowed for the processing of straw, hay and dried grass – 0700930S73
3.8In September 2007, Members approved full planning permission for the change of use to production of wood pellets. Erection of shed to store sawdust and machinery. (0701444FUL)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Panel: changed to Development Management Panel - May 2009 at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.