Resolved
RESOLVED that the Panel broadly welcome the scheme but feel that Phase II should be regarded as aspirational only at this stage. Councillor J A Gray in the Chair.
Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being decided this item on Tuesday 14 April 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Panel broadly welcome the scheme but feel that Phase II should be regarded as aspirational only at this stage. Councillor J A Gray in the Chair.
OVERVIEW AND SCRUTINY PANEL 14 APRIL 2009 CABINET 23 APRIL 2009
IMPROVEMENTS TO RIVERSIDE PARK HUNTINGDON (Report by Head of Planning, Operations and Environmental Management Services)
1. INTRODUCTION
1.1The purpose of the report is for the Cabinet to consider the comments from the public and other bodies on the ideas for improving the Riverside Park and to make a decision on what proposals will be supported and their timescale.
2. BACKGROUND INFORMATION
2.1Cabinet at its meeting on the 21st February 2008 agreed that the Council should engage with the public and others to obtain their views on a masterplan for the improvements to the Riverside Park. The estimated cost was £614,000 (see Annex 1 for breakdown) and money was included in the capital programme for this purpose.
2.2The masterplan drawn up by officers of the Council had been adapted from the preferred option of the Consultants to suit the budget for this project but still addresses many of the issues set out by the consultants namely :-
• Poor links within the park and access to the town centre mainly due to the ring road • Inadequate footpath/cycle routes and mooring points • Lack of distinguishable gateway feature and arrival point for the town centre • Negative impact of the existing car park and lack of space for park users • Ecological and landscape features are not exploited to their potential • Lack of distinctive and exciting leisure attractions or events – existing leisure facilities are under utilised (football pitches), in need of upgrading (boat hire facility) or do not appeal to a broad range of people • There are a number of visual detractors from the site and a lack of visual stimulation • There is a need to create a critical mass of facilities in the centre of the park
3.0THE COUNCIL’S MASTERPLAN
3.1For Area 1 (the formal park from the Bridge to Barracks Brook) the following improvements were suggested:
• Make the two entrance areas opposite the Bridge Hotel and along the ring road more welcoming • In association with the Bridge Hotel entrance investigate the greening of the traffic island crossing • Create a new footpath/cycleway parallel to the ring road inside the park • Create a focal point with a shelter and seating in the centre of the park • Improve the mooring facility and the paved area adjacent to Bridge Foot offices • Remove certain trees and carry out new and more appropriate tree planting • Clear river bank in certain locations to encourage easier access and improved and extra moorings • Erect standardised signs inside and through the park together with interpretation boards
3.2For Area 2 (the activity area from Barracks Brook to the north eastern edge of the playing field) the following improvements were suggested:
• Reconfigure the equipment in the play area and reduce the area in size to enable a wider landscaped walkway footpath to be created on the southern side of the car park • Retain tarmac path but remove chain link fence on the southern side of the playing field • Relocate one football pitch to Sapley Park and retain one adult sized pitch that would be sufficient to convert to 3 mini soccer pitches if necessary • Create an area of reinforced grass on part of the playing field closest to the Pavilion to accommodate the fair or circus and other events at times without losing the long stay car parking area • Create a Multi Use Games Area or youth equipment area on the playing field • De-formalise the playing field with additional planting and a less rigid management regime • Clear the river bank in certain locations to encourage easier access and improved and extra moorings. Improve the access to the slipway • Remove clutter at car park entrance by relocating recycling area and electricity pylon, removing fencing and creating a more attractive area around the pavilion and the entrance to the playing field • Encourage the redevelopment of the boat yard in accordance with the brief • Erect standardised signs and interpretation boards
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposals for Riverside Park, HuntingdonReport | 113 KB | DownloadRead as text |
Follow Overview and Scrutiny Panel (Service Support): 2006-09 - transferred to Environmental Well-Being at Huntingdonshire and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Apr 2009 | Master Plan for Land East of Sapley Square, HuntingdonRESOLVED that the Panel endorse the report and the master plan as drafted. | Decided | Open |
| 14 Apr 2009 | Huntingdon West Area Action PlanRESOLVED that the Cabinet be advised of the Panel's views on the Action Plan. | Decided | Open |
| 14 Apr 2009 | Regional Spatial Strategy Review - Cambridgeshire Development StudyRESOLVED that the Cabinet be formally notified of the Panel's views on the review of the Regional Spatial Strategy. | Decided | Open |
| 14 Apr 2009 | Review of Democratic StructureRESOLVED that the Cabinet be advised that the Panel supports the recommendations of the Democratic Structure Review W... | Deferred | Open |
| 14 Apr 2009 | Local Government & Public Involvement in Health Act - Implications for Overview & ScrutinyRESOLVED (a) that the Head of Democratic and Central Services be authorised, after consultation with the chairman of ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.